12355 W HESBY ST 91607

Certificate Information: 12355 W HESBY ST 91607

Application / Permit
23016-10000-39536
Plan Check / Job No.
B23LA21269
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/20/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 SHANGQIN XIE
Corrections Issued 11/9/2023 SHANGQIN XIE
Plan Check Approved 11/16/2023 KHUONG TRUONG
Issued 11/20/2023 APPLICANT
CofO in Progress 3/22/2024 JOSE AVILA
Permit Finaled 3/26/2024 RUBEN SALAS
CofO Issued 3/26/2024 RUBEN SALAS
Permit Finaled 3/26/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/13/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/13/2023 COLIN LOREDO
Sewer availability Cleared 11/13/2023 COLIN LOREDO
Specific Plan Cleared 11/13/2023 JOANNA MARROQUIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2023 Approved KIRK SANDERS
Underground Mechanical 12/22/2023 Partial Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 12/26/2023 Approved CHRISTOPHE COCHRAN
Sewer 12/26/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/5/2024 Approved JOSE AVILA
ELECTRICAL-Rough 1/9/2024 Approved JOSE AVILA
HVAC-Rough 1/9/2024 Approved JOSE AVILA
Shower Pan 1/11/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 1/18/2024 Approved JOSE AVILA
Interior/Exterior Lathing 1/18/2024 Approved JOSE AVILA
Shower Pan 1/18/2024 Approved JOSE AVILA
Drywall Nailing 1/24/2024 Corrections Issued JOSE AVILA
Insulation 1/24/2024 Conditional Approval JOSE AVILA
Drywall Nailing 1/29/2024 Approved JOSE AVILA
Final 2/29/2024 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 3/5/2024 Approved JOSE AVILA
Green Building Final 3/5/2024 Approved JOSE AVILA
Green Building Rough 3/5/2024 Approved JOSE AVILA
PLUMBING-Final 3/5/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Not Ready JOSE AVILA
Smoke Detectors 3/5/2024 Approved JOSE AVILA
ELECTRICAL-Final 3/6/2024 Approved JOSE AVILA
HVAC-Final 3/6/2024 Approved JOSE AVILA
Final 3/7/2024 Not Ready for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved JOSE AVILA
Final 3/22/2024 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved JOSE AVILA