4421 1/2 E MOONSTONE DR 90032

Certificate Information: 4421 1/2 E MOONSTONE DR 90032

Application / Permit
23016-10000-39493
Plan Check / Job No.
B23LA21242
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: PROPOSED CONNVERSION OF EXISTING DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/16/2024
Issuing Office
Current Status
CofO Issued on 10/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 NEHEMIAS RAMOS
Corrections Issued 11/25/2023 NEHEMIAS RAMOS
Applicant returned to address corrections 4/11/2024 KELVIN CHUONG
Plan Check Approved 4/14/2024 ZAW HAN
Issued 4/16/2024 APPLICANT
CofO in Progress 10/8/2025 ALIZAH MAYAGOITIA
Permit Finaled 10/9/2025 DEROLD HAUFF
CofO Issued 10/9/2025 DEROLD HAUFF
Permit Finaled 10/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 1/8/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/9/2024 WALLIE JONG
Grading Pre-Inspection Cleared 1/9/2024 ROBERT HUGHES
"D" conditions Cleared 1/23/2024 MATHEW QUAN
"Q" conditions Cleared 1/23/2024 MATHEW QUAN
Construction near power lines Cleared 2/23/2024 RIDWAN HARDY
Address approval Cleared 4/11/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/28/2024 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/28/2024 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 11/13/2024 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/3/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 6/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 6/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/3/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 7/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 7/30/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 8/1/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 9/22/2025 Approved ALIZAH MAYAGOITIA
Final 9/22/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 9/22/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 9/22/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/22/2025 Approved ALIZAH MAYAGOITIA
Final 10/3/2025 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 10/3/2025 Approved ALIZAH MAYAGOITIA
Final 10/7/2025 OK to Issue CofO ALIZAH MAYAGOITIA