6108 W SUNSET BLVD 90028
Certificate Information: 6108 W SUNSET BLVD 90028
- Application / Permit
- 23016-10000-39398
- Plan Check / Job No.
- B23LA21152
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- CHANGE OF USE FROM OFFICE TO BEAUTY SALON.
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Current Status
- CofO Issued on 10/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2023 | JOE VO |
| Corrections Issued | 11/13/2023 | JOE VO |
| Applicant returned to address corrections | 11/21/2023 | LUKE GONZALES |
| Plan Check Approved | 12/13/2023 | JOE VO |
| Issued | 2/23/2024 | APPLICANT |
| CofO in Progress | 10/7/2024 | TIMOTHY POWELL |
| Permit Finaled | 10/10/2024 | RAFAEL ESPINOZA |
| CofO Issued | 10/10/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 10/10/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 11/20/2023 | RAFAEL FONTES |
| "D" conditions | Cleared | 11/22/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 11/22/2023 | SPENCER WEJROWSKI |
| Address approval | Cleared | 12/1/2023 | AMBER CAMPBELL |
| Redevelopment Project Area | Cleared | 12/1/2023 | YASMINE BASHIRI |
| Sewer availability | Cleared | 12/1/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2023 | AMBER CAMPBELL |
Contact Information
| Contractor | K T Construction; Lic. No.: 963677-B | 7850 LA MERCED RD ROSEMEAD, CA 91770 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 6/3/2024 | Corrections Issued | TIMOTHY POWELL |
| Light Gage Steel Frame | 6/3/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 6/5/2024 | Approved | TIMOTHY POWELL |
| Light Gage Steel Frame | 6/5/2024 | Approved | TIMOTHY POWELL |
| Final | 7/11/2024 | Partial Inspection | TIMOTHY POWELL |
| Reinforced Masonry Frame | 7/11/2024 | Not Required | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 7/11/2024 | Not Required | TIMOTHY POWELL |
| Final | 7/13/2024 | Off-Hour Fees Due | |
| Reinforced Masonry Frame | 7/13/2024 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 7/13/2024 | Off-Hour Fees Due | |
| Smoke Detectors | 7/13/2024 | Off-Hour Fees Due | |
| Final | 7/23/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 9/23/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Reinforced Masonry Frame | 9/23/2024 | Approved | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 9/23/2024 | Approved | TIMOTHY POWELL |
| Final | 10/4/2024 | OK to Issue CofO | TIMOTHY POWELL |