7306 N YARMOUTH AVE 91335
Certificate Information: 7306 N YARMOUTH AVE 91335
- Application / Permit
- 23016-10000-39393
- Plan Check / Job No.
- B23LA21146
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage into accessory dwelling unit per LAMC 12.22 A33 (c) and (d) and attic space to habitable space. All work per engineer.
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Current Status
- CofO Issued on 8/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2023 | VICTOR CHEN |
| Corrections Issued | 11/11/2023 | VICTOR CHEN |
| Building Plans Picked Up | 11/14/2023 | APPLICANT |
| Plan Check Approved | 2/28/2024 | DANIEL SANJUAN |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 8/27/2024 | JEFFREY BULL |
| CofO in Progress | 8/27/2024 | SEAN WIRCH |
| Permit Finaled | 8/28/2024 | JOHN JANSON |
| CofO Issued | 8/28/2024 | JOHN JANSON |
| Permit Finaled | 8/28/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 11/20/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2023 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 2/6/2024 | EDGAR PASCUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/15/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 3/15/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 3/15/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 5/9/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 5/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 5/9/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 5/9/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/17/2024 | Approved | JEFFREY BULL |
| Shower Pan | 5/17/2024 | Approved | JEFFREY BULL |
| Insulation | 5/24/2024 | Not Ready for Inspection | JEFFREY BULL |
| Interior/Exterior Lathing | 5/24/2024 | Approved | JEFFREY BULL |
| Insulation | 5/31/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 6/4/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/9/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 8/9/2024 | Approved | JEFFREY BULL |
| Final | 8/9/2024 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 8/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 8/9/2024 | Approved | JEFFREY BULL |
| HVAC-Final | 8/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 8/9/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 8/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| Final | 8/15/2024 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 8/15/2024 | Approved | JEFFREY BULL |
| HVAC-Final | 8/15/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 8/15/2024 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 8/27/2024 | Approved | JEFFREY BULL |
| Final | 8/27/2024 | OK to Issue CofO | JEFFREY BULL |