9419 S AIRPORT BLVD 90045

Certificate Information: 9419 S AIRPORT BLVD 90045

Application / Permit
23016-10000-39375
Plan Check / Job No.
B23LA21125
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
**ePlan**LAX APM Aux Curb** Modifications to Existing Economy Lot Parking Structure include removing existing curb, removing existing striping, removing existing EV charging stations, relocating prefabricated metal gate from existing location to new location, revising signage inside of parking structure
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
Permit Finaled on 11/20/2025

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/15/2023 VARAND SARKISIAN
Corrections Issued 11/21/2023 VARAND SARKISIAN
Quality Review Completed 11/21/2023 LIPING TENG
Applicant returned to address corrections 3/4/2024 VARAND SARKISIAN
Plan Check Approved 12/24/2024 VARAND SARKISIAN
Issued 1/6/2025 APPLICANT
Permit Finaled-Status Void 7/23/2025 NICK LAROCCA
Re-Activate Permit 9/25/2025 NICK LAROCCA
Permit Finaled 11/20/2025 RICARDO ROBLES

Permit Application Clearance Information

City owned building/parcel Cleared 5/20/2024 LIPING TENG
Project Permit Cleared 7/18/2024 ALEXANDER GARCIA
Airport buildings Cleared 10/7/2024 ANDREW KO
Green Code Cleared 12/11/2024 MICHAEL AYERS
DAS Clearance Cleared 12/12/2024 Lily Teng

Contact Information

Contractor Swinerton Builders; Lic. No.: 92-B       ,
Engineer Nadal,, Mark; Lic. No.: S5494 4964 BLACKHORSE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 4/9/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/9/2025 Approved NICK LAROCCA
Deputy Grading 4/10/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/10/2025 Approved NICK LAROCCA
Deputy Grading 4/11/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/11/2025 Approved NICK LAROCCA
Deputy Grading 4/14/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/14/2025 Approved NICK LAROCCA
Deputy Grading 4/15/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/15/2025 Approved NICK LAROCCA
Pre-Inspection 4/29/2025 Approved NICK LAROCCA
Deputy Grading 5/1/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/1/2025 Approved NICK LAROCCA
Deputy Grading 5/2/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/2/2025 Approved NICK LAROCCA
Deputy Grading 5/5/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/5/2025 Approved NICK LAROCCA
Deputy Grading 5/6/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/6/2025 Approved NICK LAROCCA
Deputy Grading 5/7/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/7/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 6/16/2025 Approved NICK LAROCCA
Deputy Grading 7/23/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/23/2025 Approved NICK LAROCCA
Final 7/23/2025 Partial Inspection NICK LAROCCA
Green Building Final 7/23/2025 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Approved NICK LAROCCA
Smoke Detectors 7/23/2025 Approved NICK LAROCCA
Deputy Grading 7/24/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/24/2025 Approved NICK LAROCCA
Deputy Grading 7/25/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/25/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 9/26/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 9/29/2025 Conditional Approval RICARDO ROBLES
Deputy Drilled-In Anchors 9/30/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 10/1/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 10/2/2025 Approved NICK LAROCCA
Deputy Grading 10/8/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/8/2025 Approved NICK LAROCCA
Deputy Grading 10/9/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/9/2025 Approved NICK LAROCCA
Deputy Grading 10/10/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/10/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/17/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 10/31/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/6/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/7/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 11/12/2025 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/12/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 11/13/2025 Conditional Approval RICARDO ROBLES
Deputy Reinf. Concrete 11/13/2025 Conditional Approval RICARDO ROBLES
Deputy Drilled-In Anchors 11/14/2025 Conditional Approval RICARDO ROBLES
Deputy Reinf. Concrete 11/14/2025 Conditional Approval RICARDO ROBLES
Final 11/19/2025 Partial Approval RICARDO ROBLES
Final 11/20/2025 Permit Finaled RICARDO ROBLES