848 1/2 S DETROIT ST 90036
Certificate Information: 848 1/2 S DETROIT ST 90036
- Application / Permit
- 23016-10000-39151
- Plan Check / Job No.
- B23LA21026
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PART OF (E) 2-STORY DUPLEX TO A.D.U. 726SF PER LAMC 12.22 A 33(c) AND (e)
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2023 | SHANGQIN XIE |
| Corrections Issued | 11/15/2023 | SHANGQIN XIE |
| Plan Check Approved | 2/15/2024 | SHANGQIN XIE |
| Issued | 8/27/2024 | APPLICANT |
| CofO in Progress | 11/18/2025 | RONNIE MINDANAO |
| No Progress | 11/19/2025 | DEROLD HAUFF |
| CofO in Progress | 11/19/2025 | DEROLD HAUFF |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
| CofO Issued | 11/29/2025 | DEROLD HAUFF |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/7/2023 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 12/15/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 12/26/2023 | ARNULFO CHAMU |
| HPOZ | Cleared | 2/13/2024 | ERIK VAN BREENE |
Contact Information
| Contractor | Lapointe Brothers Inc; Lic. No.: 1037066-B | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/6/2025 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/12/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/10/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 3/10/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 3/10/2025 | Approved | RONNIE MINDANAO |
| Service/Power Release | 3/25/2025 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 3/28/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 3/28/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/7/2025 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Partial Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | RONNIE MINDANAO |
| Insulation | 4/17/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 4/28/2025 | Approved | RONNIE MINDANAO |
| Insulation | 4/28/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/5/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 5/5/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 10/2/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 10/2/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 10/2/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Final | 10/2/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 10/2/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 10/2/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/20/2025 | Approved | RONNIE MINDANAO |
| Final | 10/20/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 10/20/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 10/20/2025 | Approved | RONNIE MINDANAO |
| Smoke Detectors | 10/20/2025 | Approved | RONNIE MINDANAO |
| Final | 10/22/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 10/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 11/3/2025 | Partial Approval | RONNIE MINDANAO |
| Final | 11/17/2025 | OK to Issue CofO | RONNIE MINDANAO |