319 N OXFORD AVE 90004
Certificate Information: 319 N OXFORD AVE 90004
- Application / Permit
- 23016-10000-39137
- Plan Check / Job No.
- B23LA21021
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Soft-story retrofit of existing apartment building using Special Cantilever Column System and Wood Shear Wall.
- Permit Issued
- Issued on 2/5/2025
- Issuing Office
- Current Status
- CofC Issued on 2/17/2026
Permit Application Status History
| Submitted | 11/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | HANS SANTIAGO |
| Corrections Issued | 11/13/2023 | HANS SANTIAGO |
| Quality Review Completed | 11/13/2023 | CHARMIE HUYNH |
| Plan Check Approved | 2/12/2024 | ANDREW SANTIAGO |
| Issued | 2/5/2025 | APPLICANT |
| OK for CofC | 2/17/2026 | ERNESTO CORRAL |
| CofC Issued | 2/17/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 11/17/2023 | YASMINE BASHIRI |
| Historic Resource Verification | Cleared | 1/9/2024 | YASMINE BASHIRI |
| Tenant Habitability Plan | Cleared | 1/21/2025 | RICARDO BOHORQUEZ |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | A T A Construction Services; Lic. No.: 974795-B | 7199 OLD 215 FRONTAGE RD MORENO VALLEY, CA 92553 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2025 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 6/3/2025 | No Access for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/12/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/2/2025 | No Access for Inspection | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/10/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/17/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Structural Steel Frame | 7/17/2025 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/17/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 7/18/2025 | Corrections Issued | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 7/21/2025 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 7/21/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 7/21/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/22/2025 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Corrections Issued | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 8/7/2025 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/7/2025 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/7/2025 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 8/14/2025 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/14/2025 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/21/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 8/21/2025 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 8/29/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/29/2025 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 9/23/2025 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/24/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 10/9/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/9/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 2/17/2026 | OK for CofC | ERNESTO CORRAL |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | ERNESTO CORRAL |
| Smoke Detectors | 2/17/2026 | Approved | ERNESTO CORRAL |