6250 W HOLLYWOOD BLVD 90028

Certificate Information: 6250 W HOLLYWOOD BLVD 90028

Application / Permit
23016-10000-38902
Plan Check / Job No.
B23LA20900
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
eplan PARTIAL RENOVATION OF EXISTING RESTAURANT SPACE ( NO WORK ON KITCHEN )
Permit Issued
Issued on 3/18/2024
Issuing Office
Current Status
Permit Finaled on 3/12/2025

Permit Application Status History

Submitted 11/17/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 MOHAMMAD ESMAILI
Corrections Issued 11/22/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 1/30/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/15/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/8/2024 MOHAMMAD ESMAILI
Plan Check Approved 3/15/2024 MOHAMMAD ESMAILI
Issued 3/18/2024 APPLICANT
Permit Finaled 3/12/2025 TIMOTHY POWELL

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 3/13/2024 DOMINIQUE MEDINA
Food establishment approval Cleared 3/15/2024 LACDHS APPROVED

Contact Information

Architect Villegas,, Gregory M; Lic. No.: C26518 2330 VANGUARD WAY APT M102      COSTA MESA, CA 92626
Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 4/4/2024 Not Ready for Inspection TIMOTHY POWELL
Light Gage Steel Frame 5/3/2024 Conditional Approval DARRYL ARNOLD
Drywall Nailing 5/13/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 6/6/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 6/11/2024 Partial Approval TIMOTHY POWELL
Final 8/30/2024 Partial Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 8/30/2024 Approved TIMOTHY POWELL
Final 1/22/2025 Partial Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Not Ready TIMOTHY POWELL
Final 3/12/2025 Permit Finaled TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Approved TIMOTHY POWELL