3325 W 66TH PL 90043

Certificate Information: 3325 W 66TH PL 90043

Application / Permit
23016-10000-38880
Plan Check / Job No.
B23LA20890
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing Detached Garage to Accessory Dwelling Unit (378 S.F.) per CA GC 65852.2(e)(1)(A) . Work per Wood Frame Prescriptive Provisions .
Permit Issued
Issued on 1/18/2024
Issuing Office
Metro
Current Status
Issued on 1/18/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2023 APPLICANT
Assigned to Plan Check Engineer 11/3/2023 JOSEPH RAFOLS
Corrections Issued 11/3/2023 JOSEPH RAFOLS
Issued 1/18/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/17/2023 AMBER CAMPBELL
Sewer availability Cleared 11/17/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 11/21/2023 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/20/2024 Approved JOSE MACIAS
Pre-Inspection 4/1/2024 Not Ready for Inspection JOSE MACIAS
Footing/Foundation/Slab 5/14/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 6/27/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 6/27/2024 Not Ready for Inspection JOSE MACIAS
Pre-Inspection 6/27/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 7/9/2024 Approved JOSE MACIAS
Deputy Drilled-In Anchors 7/17/2024 Conditional Approval JOSE MACIAS
BUILDING-Rough-Frame 7/23/2024 Not Ready for Inspection JOSE MACIAS
Footing/Foundation/Slab 7/23/2024 Corrections Issued JOSE MACIAS
Green Building Rough 7/23/2024 Not Ready for Inspection JOSE MACIAS
Footing/Foundation/Slab 7/29/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 8/6/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 10/30/2024 Not Ready for Inspection AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 10/30/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 11/13/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 11/13/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 2/21/2025 Approved MICHAEL LEWIS
ELECTRICAL-Rough 3/18/2025 Partial Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 6/2/2025 Corrections Issued WAYNE REGESTER
Green Building Rough 6/2/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Rough 6/2/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Not Required WAYNE REGESTER
BUILDING-Rough-Frame 6/18/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Rough 6/18/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 7/1/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Rough 7/1/2025 Approved WAYNE REGESTER
PLUMBING-Final 7/1/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Rough 7/1/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 7/11/2025 Corrections Issued MICHAEL LEWIS
Green Building Rough 7/11/2025 Corrections Issued MICHAEL LEWIS
HVAC-Rough 7/11/2025 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 9/23/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 9/23/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 9/23/2025 Corrections Issued SALVADOR MARTINEZ