11745 W ARMINTA ST 91605
Certificate Information: 11745 W ARMINTA ST 91605
- Application / Permit
- 23016-10000-38834
- Plan Check / Job No.
- B23LA20868
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 1-story detached garage with rec-room into ADU per State law, all work per WFPP
- Permit Issued
- Issued on 12/1/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2023 | AUNG SOE |
| Corrections Issued | 11/9/2023 | AUNG SOE |
| Applicant returned to address corrections | 11/28/2023 | WEIJIAN HUANG |
| Plan Check Approved | 11/29/2023 | MINA HABILI |
| Issued | 12/1/2023 | APPLICANT |
| CofO in Progress | 10/4/2024 | MATTHEW NELSON |
| CofO Issued | 10/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 11/14/2023 | CARLOS RAMIREZ |
| Clean Up Green Up | Cleared | 11/22/2023 | YINGSHI HUANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/26/2024 | Approved | MATTHEW NELSON |
| Pre-Inspection | 3/26/2024 | Partial Inspection | MATTHEW NELSON |
| Underground Mechanical | 3/26/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/17/2024 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 4/17/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 4/17/2024 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/25/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/25/2024 | Approved | MATTHEW NELSON |
| Underground Mechanical | 4/25/2024 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/10/2024 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 5/31/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Approved | MATTHEW NELSON |
| Insulation | 5/31/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/5/2024 | Approved | MATTHEW NELSON |
| Pre-Inspection | 6/27/2024 | Approved | MATTHEW NELSON |
| Pre-Inspection | 7/26/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/30/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 9/23/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 9/23/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 9/23/2024 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 9/23/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 9/23/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 9/23/2024 | Approved | MATTHEW NELSON |
| Gas Test | 9/24/2024 | Approved | MATTHEW NELSON |
| Final | 10/2/2024 | No Access for Inspection | ROBERT GOLD |
| Green Building Final | 10/2/2024 | No Access for Inspection | ROBERT GOLD |
| Final | 10/4/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 10/4/2024 | Approved | MATTHEW NELSON |