10224 W CHARING CROSS ROAD 90024
Certificate Information: 10224 W CHARING CROSS ROAD 90024
- Application / Permit
- 23016-10000-38757
- Plan Check / Job No.
- B23LA20839
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL TO EXISTING 1-STY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 2/2/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/31/2025
Permit Application Status History
| Submitted | 11/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | PRANITA SHAH |
| Corrections Issued | 11/14/2023 | PRANITA SHAH |
| Quality Review Completed | 11/28/2023 | GARO TELMI |
| Applicant returned to address corrections | 12/27/2023 | PRANITA SHAH |
| Plan Check Approved | 1/29/2024 | PRANITA SHAH |
| Issued | 2/2/2024 | APPLICANT |
| Permit Finaled | 1/31/2025 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 11/20/2023 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 12/6/2023 | RUSSELL BONVOULOIR |
Contact Information
| Contractor | M G Partners Inc; Lic. No.: 886387-B | , |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: NA40985 | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/20/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 2/20/2024 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 2/26/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/26/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/12/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/12/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/13/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/18/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/27/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 3/27/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 3/27/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/27/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 4/8/2024 | Partial Approval | SEAN HAUPT |
| Drywall Nailing | 4/11/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 4/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/23/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 4/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 5/14/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 5/14/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/23/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/3/2024 | Conditional Approval | STEPHANIE SWANSON |
| Shower Pan | 6/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 6/7/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 6/25/2024 | Approved | CHRISTOPHER WILSON |
| Final | 1/31/2025 | Permit Finaled | STEPHANIE SWANSON |
| Green Building Final | 1/31/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 1/31/2025 | Approved | STEPHANIE SWANSON |