5416 W WILSHIRE BLVD 90036

Certificate Information: 5416 W WILSHIRE BLVD 90036

Application / Permit
23016-10000-38721
Plan Check / Job No.
B23LA20815
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
New tenant improvement and change of use from existing retail space to new business office.
Permit Issued
Issued on 9/12/2024
Issuing Office
Current Status
CofO Issued on 4/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 JOE VO
Assigned to Zoning Architect 12/1/2023 JOE VO
Corrections Issued 12/5/2023 JOE VO
Quality Review Completed 12/5/2023 GARO TELMI
Applicant returned to address corrections 2/21/2024 JOE VO
Applicant returned to address corrections 3/5/2024 JOE VO
Plan Check Approved 4/9/2024 JOE VO
Issued 9/12/2024 APPLICANT
TCO Issued (Expire Date: 09-24-2025) 3/28/2025 ERNESTO CORRAL
Permit Finaled 4/28/2025 ERNESTO CORRAL
CofO Issued 4/28/2025 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 12/15/2023 MAXFIELD VERMY
CPC Cleared 12/15/2023 MAXFIELD VERMY
Supp. Use District POD/CDO/TDO Cleared 12/15/2023 MAXFIELD VERMY
ZA Case Cleared 12/15/2023 MAXFIELD VERMY
ZI Cleared 12/15/2023 MAXFIELD VERMY
Historic monument Cleared 12/18/2023 LAMBERT GIESSINGER
Green Code Cleared 3/5/2024 DONALD CRICHLOW
Zoning Plan Check Cleared 3/5/2024 JOE VO
DAS Clearance Cleared 3/19/2024 ELIZABETH TOMS
Eng Process Fee Ord 176,300 Cleared 4/8/2024 AMY SHUM
Sewer availability Cleared 4/8/2024 AMY SHUM

Contact Information

Architect Kaliski,, John Ethan; Lic. No.: C17945 3780 WILSHIRE BLVD #500      LOS ANGELES, CA 90010
Contractor S O S Enterprises Inc; Lic. No.: 696896-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2024 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 9/17/2024 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 9/23/2024 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 9/24/2024 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 9/27/2024 Approved MARTIN TAVITIAN
Structural Steel Frame 10/29/2024 Not Ready for Inspection MARTIN TAVITIAN
Insulation 1/23/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Insulation 1/27/2025 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 1/27/2025 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 1/30/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 1/31/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Drywall Nailing 2/7/2025 Approved MARTIN TAVITIAN
Final 3/21/2025 Partial Approval ALFREDO LOPEZ
Green Building Final 3/21/2025 Approved ALFREDO LOPEZ
Green Building Rough 3/21/2025 Approved ALFREDO LOPEZ
METHANE-Final 3/21/2025 Approved ALFREDO LOPEZ
METHANE-Rough 3/21/2025 Approved ALFREDO LOPEZ
Pre-Inspection 3/21/2025 Approved ALFREDO LOPEZ
Reinforced Masonry Frame 3/21/2025 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Required ALFREDO LOPEZ
Smoke Detectors 3/21/2025 Approved ALFREDO LOPEZ
Pre-Inspection 3/27/2025 Conditional Approval ALFREDO LOPEZ
Final 3/28/2025 OK for TCO EDWIN GREGORYONA
Final 4/21/2025 Partial Inspection ALFREDO LOPEZ