1307 S OCEAN FRONT WALK 90291
Certificate Information: 1307 S OCEAN FRONT WALK 90291
- Application / Permit
- 23016-10000-38123
- Plan Check / Job No.
- B23LA20519
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- Tenant Improvement to existing take out restaurant.
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 7/8/2024
Permit Application Status History
| Plan Check Approved | 1/30/2024 | SALVADOR QUINTANILLA |
| Issued | 2/1/2024 | APPLICANT |
| Permit Finaled | 7/1/2024 | FARHAD DADBIN |
Permit Application Clearance Information
| Food Service Establishment | Cleared | 1/18/2024 | PAWAN VERMA |
| Food establishment approval | Cleared | 1/30/2024 | LACDHS APPROVED |
Contact Information
| Contractor | Gomringer Construction Services; Lic. No.: 1077715-B | 528 W GREENDALE STREET COVINA, CA 91723 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2024 | No Access for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 3/14/2024 | Partial Approval | RICARDO ROBLES |
| Pre-Inspection | 3/14/2024 | Partial Approval | RICARDO ROBLES |
| Excavation/Setback/Form/Re-Bar | 3/28/2024 | Approved | RICARDO ROBLES |
| Footing/Foundation/Slab | 3/28/2024 | Approved | RICARDO ROBLES |
| Light Gage Steel Frame | 4/5/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 4/11/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 4/24/2024 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 5/17/2024 | Approved | FARHAD DADBIN |
| Final | 5/31/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 6/5/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 6/5/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 6/25/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 7/1/2024 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 7/1/2024 | Approved | FARHAD DADBIN |