3300 W SLAUSON AVE 90043
Certificate Information: 3300 W SLAUSON AVE 90043
- Application / Permit
- 23016-10000-38067
- Plan Check / Job No.
- B23LA20478
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- PROPOSED TENANT IMPROVEMENT (T.I.) FOR VALLARTA SUPERMARKET SPACE.
- Permit Issued
- Issued on 7/26/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/21/2025
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | JOE VO |
| Assigned to Zoning Architect | 12/1/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 12/9/2023 | JOE VO |
| Quality Review Completed | 12/11/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 3/8/2024 | JOE VO |
| Plan Check Approved | 7/25/2024 | JOE VO |
| Issued | 7/26/2024 | APPLICANT |
| Permit Finaled | 4/18/2025 | ALFREDO LOPEZ |
Permit Application Clearance Information
| "D" conditions | Cleared | 1/17/2024 | YINGSHI HUANG |
| Specific Plan | Cleared | 1/17/2024 | YINGSHI HUANG |
| Historic Resource Verification | Cleared | 2/2/2024 | ELIZABETH GALLARDO |
| Redevelopment Project Area | Cleared | 2/2/2024 | ELIZABETH GALLARDO |
| Hydrant and Access approval | Cleared | 2/26/2024 | KURT CORRAL |
| Food Service Establishment | Cleared | 2/29/2024 | RAMESHBHAIR PATEL |
| Green Code | Cleared | 3/20/2024 | Shangqin Xie |
| DAS Clearance | Cleared | 4/4/2024 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 4/29/2024 | ARSALAN SHABESTARI |
| Food establishment approval | Cleared | 7/25/2024 | LACDHS APPROVED |
Contact Information
| Architect | Budetti,, Robert Peter; Lic. No.: NA23757 | , |
| Contractor | Padelford A J & Son Inc; Lic. No.: 222840-B | , |
| Engineer | Nagarajan,, Sivaram; Lic. No.: NA6349 | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 9/30/2024 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 11/21/2024 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 11/21/2024 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 1/2/2025 | Partial Approval | ALFREDO LOPEZ |
| Final | 4/18/2025 | Permit Finaled | ALFREDO LOPEZ |
| Green Building Final | 4/18/2025 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 4/18/2025 | Approved | ALFREDO LOPEZ |