2010 N HIGHLAND AVE 90068

Certificate Information: 2010 N HIGHLAND AVE 90068

Application / Permit
23016-10000-37947
Plan Check / Job No.
B23LA20445
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePLAN. CHANGE OF USE AND OCCUPANCY FROM (E) 3-STORY 62 GUESTROOMS MOTEL (R1) TO MULTIFAMILY HOUSING PROGRAM (R2) PER GCS 50675.1.3. CONVERT PORTION OF GARAGE INTO STORAGE AND OFFICES. PROJECT HOMEKEY.
Permit Issued
Issued on 6/13/2024
Issuing Office
Current Status
CofO in Progress on 4/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2023 APPLICANT
Assigned to Plan Check Engineer 11/2/2023 KEVIN MORALES
Corrections Issued 11/15/2023 KEVIN MORALES
Quality Review Completed 11/16/2023 EUGENE BARBEAU
Applicant returned to address corrections 2/7/2024 KEVIN MORALES
Applicant returned to address corrections 3/15/2024 KEVIN MORALES
Applicant returned to address corrections 5/22/2024 KEVIN MORALES
Plan Check Approved 6/6/2024 KEVIN MORALES
Issued 6/13/2024 APPLICANT
TCO Issued (Expire Date: 04-08-2026) 10/10/2025 RAFAEL ESPINOZA
CofO in Progress 4/7/2026 RAFAEL ESPINOZA
TCO Issued (Expire Date: 10-10-2026) 4/13/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

"Q" conditions Cleared 12/14/2023 STEVEN WECHSLER
Miscellaneous Cleared 12/14/2023 STEVEN WECHSLER
Sewer availability Cleared 12/20/2023 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 1/18/2024 ARNULFO CHAMU
Density Bonus Cleared 1/25/2024 MARITES CUNANAN
Green Code Cleared 2/22/2024 Rodolfo Arias
Fire Marshal Fire Life Safety Cleared 3/23/2024 RONILO MULAWIN
Low Impact Development (LID) Cleared 3/25/2024 MARTIN FRAGOSO
DAS Clearance Cleared 5/28/2024 Rodolfo Arias
Public Housing Cleared 5/28/2024 SAMANTHA MARSCH

Contact Information

Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/23/2024 Partial Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 8/26/2024 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 9/17/2024 Approved RAFAEL CORTES
Special/Order Compliance 9/17/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 10/4/2024 Corrections Issued RAFAEL ESPINOZA
Pre-Inspection 10/23/2024 Not Ready for Inspection JACOB MYERS
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved RAFAEL CORTES
Light Gage Steel Frame 12/3/2024 Corrections Issued RAFAEL CORTES
Pre-Inspection 12/12/2024 Approved RAFAEL CORTES
Interior/Exterior Lathing 1/21/2025 Partial Inspection EDWIN GREGORYONA
Pre-Inspection 1/23/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 2/6/2025 Approved RAFAEL CORTES
Pre-Inspection 2/13/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 2/20/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 2/24/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 2/26/2025 Partial Approval RAFAEL CORTES
Insulation 2/27/2025 No Access for Inspection RAFAEL CORTES
Pre-Inspection 2/27/2025 No Access for Inspection RAFAEL CORTES
Pre-Inspection 3/4/2025 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 3/5/2025 Partial Approval RAFAEL CORTES
Insulation 3/17/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 3/19/2025 Not Ready for Inspection RAFAEL CORTES
Deputy Drilled-In Anchors 3/20/2025 Conditional Approval RAFAEL CORTES
Insulation 3/21/2025 Corrections Issued RAFAEL CORTES
Drywall Nailing 3/26/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 3/26/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 3/28/2025 Partial Approval RAFAEL CORTES
Insulation 3/28/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 4/4/2025 No Access for Inspection RAFAEL CORTES
Light Gage Steel Frame 4/7/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 4/10/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 4/15/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 4/17/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 4/25/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 5/1/2025 Partial Approval RAFAEL CORTES
Insulation 5/6/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/6/2025 Partial Approval EDWIN GREGORYONA
Pre-Inspection 5/7/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 5/9/2025 Partial Approval RAFAEL CORTES
Insulation 5/16/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 5/22/2025 Partial Approval RAFAEL CORTES
Insulation 5/28/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 6/4/2025 Partial Approval RAFAEL CORTES
Wood Frame 6/4/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 6/11/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 6/18/2025 Approved RAFAEL CORTES
Pre-Inspection 6/23/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 6/25/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 6/27/2025 Approved MARTIN TAVITIAN
Light Gage Steel Frame 7/1/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 7/9/2025 Partial Approval DAVID BURKHEAD
Pre-Inspection 7/10/2025 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 7/11/2025 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 7/14/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/16/2025 Partial Approval EDWIN GREGORYONA
Pre-Inspection 7/17/2025 No Access for Inspection RAFAEL CORTES
Wood Frame 7/28/2025 Partial Approval EDWIN GREGORYONA
Pre-Inspection 7/30/2025 Partial Approval RAFAEL CORTES
Wood Frame 8/1/2025 Partial Approval RAFAEL CORTES
Insulation 8/6/2025 Partial Approval RAFAEL CORTES
Insulation 8/11/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 8/13/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 8/19/2025 Partial Approval EDWIN GREGORYONA
Final 9/18/2025 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 9/18/2025 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 9/18/2025 Not Ready for Inspection EDWIN GREGORYONA
Special/Order Compliance 9/19/2025 Not Ready for Inspection RAFAEL CORTES
Final 9/25/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 9/25/2025 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 9/25/2025 Not Ready for Inspection RAFAEL CORTES
Final 10/3/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 10/3/2025 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 10/3/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 10/6/2025 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 10/7/2025 Approved RAFAEL CORTES
Pre-Inspection 2/17/2026 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 2/23/2026 Partial Approval RAFAEL CORTES
Special/Order Compliance 3/10/2026 Approved RAFAEL CORTES
Pre-Inspection 3/16/2026 Partial Approval RAFAEL CORTES
Final 4/7/2026 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 4/7/2026 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 4/7/2026 Approved RAFAEL ESPINOZA