1724 E CENTURY BLVD 90002
Certificate Information: 1724 E CENTURY BLVD 90002
- Application / Permit
- 23016-10000-37940
- Plan Check / Job No.
- B23LA19129
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (23) Recreation Room
- Work Description
- ePLAN. REMODEL (E) COMMUNITY/RECREATION BUILDING
- Permit Issued
- Issued on 2/16/2024
- Issuing Office
- Current Status
- Permit Finaled on 7/15/2025
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | KEVIN MORALES |
| Corrections Issued | 10/27/2023 | KEVIN MORALES |
| Quality Review Completed | 10/31/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 12/29/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 2/1/2024 | KEVIN MORALES |
| Plan Check Approved | 2/7/2024 | KEVIN MORALES |
| Issued | 2/16/2024 | APPLICANT |
| Permit Finaled | 7/15/2025 | DARRYL ARNOLD |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 11/8/2023 | JENNIFER SU |
| Low Impact Development (LID) | Cleared | 12/14/2023 | MARTIN FRAGOSO |
| Public Housing | Cleared | 1/25/2024 | JOEL LAUNCHBAUGH |
| Tenant Habitability Plan | Cleared | 1/26/2024 | RICARDO BOHORQUEZ |
| Green Code | Cleared | 1/30/2024 | AARON COSTA |
| DAS Clearance | Cleared | 2/5/2024 | KEVIN MORALES |
Contact Information
| Contractor | Burch J Aldric Construction; Lic. No.: 871255-B | 1255 LINDA RIDGE ROAD PASADENA, CA 91103 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Approved | DARRYL ARNOLD |
| Final | 5/13/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Final | 5/13/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/13/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 6/3/2025 | Conditional Approval | ALFREDO LOPEZ |
| Green Building Final | 6/3/2025 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 6/3/2025 | Approved | ALFREDO LOPEZ |
| Final | 7/9/2025 | Conditional Approval | ALFREDO LOPEZ |
| Final | 7/15/2025 | Permit Finaled | DARRYL ARNOLD |