6117 W LINDENHURST AVE 90048

Certificate Information: 6117 W LINDENHURST AVE 90048

Application / Permit
23016-10000-37870
Plan Check / Job No.
B23LA20397
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
convert existing 1 story detached garage into ADU per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 3/29/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 10/30/2023 AUNG SOE
Corrections Issued 11/4/2023 AUNG SOE
Building Plans Picked Up 11/7/2023 APPLICANT
Plan Check Approved 3/7/2024 NGHI SU
Issued 3/29/2024 APPLICANT
CofO in Progress 4/8/2025 EVAN COOPER
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

CPC Cleared 11/13/2023 JOE TAM
Construction near power lines Cleared 2/10/2024 RIDWAN HARDY
Construction within easement Cleared 2/10/2024 RIDWAN HARDY
Address approval Cleared 2/22/2024 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 2/22/2024 ARNULFO CHAMU
Sewer availability Cleared 2/22/2024 ARNULFO CHAMU

Contact Information

Contractor Owner-Builder       ,
Engineer Muller,, Paul; Lic. No.: C83707 338 VIEWPARK CIRCLE      SAN JOSE, CA 95136

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 10/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 10/23/2024 Corrections Issued MEL KHACHATOURIAN
Sewer 10/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
Underground Mechanical 10/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 10/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/14/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 11/14/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 11/14/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 11/14/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/22/2024 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 11/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 11/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/26/2024 Corrections Issued MEL KHACHATOURIAN
BUILDING-Rough-Frame 12/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 12/11/2024 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 12/11/2024 Approved MEL KHACHATOURIAN
Rough-Elec/Plmb/HVAC 12/11/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 12/17/2024 Approved SEAN HAUPT
Insulation 12/17/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 12/24/2024 Partial Approval MEL KHACHATOURIAN
Drywall Nailing 12/30/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 12/30/2024 Approved SEAN HAUPT
Shower Pan 12/30/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 1/3/2025 Approved SEAN HAUPT
Sewer 1/24/2025 Approved MEL KHACHATOURIAN
Underground Mechanical 1/24/2025 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/17/2025 Approved ARAM AVEDISIAN
Final 3/17/2025 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Not Required ARAM AVEDISIAN
Smoke Detectors 3/17/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Final 4/8/2025 Approved EVAN COOPER
Final 4/8/2025 OK to Issue CofO EVAN COOPER
HVAC-Final 4/8/2025 Approved EVAN COOPER
PLUMBING-Final 4/8/2025 Approved EVAN COOPER