6117 W LINDENHURST AVE 90048
Certificate Information: 6117 W LINDENHURST AVE 90048
- Application / Permit
- 23016-10000-37870
- Plan Check / Job No.
- B23LA20397
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- convert existing 1 story detached garage into ADU per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 3/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2023 | AUNG SOE |
| Corrections Issued | 11/4/2023 | AUNG SOE |
| Building Plans Picked Up | 11/7/2023 | APPLICANT |
| Plan Check Approved | 3/7/2024 | NGHI SU |
| Issued | 3/29/2024 | APPLICANT |
| CofO in Progress | 4/8/2025 | EVAN COOPER |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| CPC | Cleared | 11/13/2023 | JOE TAM |
| Construction near power lines | Cleared | 2/10/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/10/2024 | RIDWAN HARDY |
| Address approval | Cleared | 2/22/2024 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | ARNULFO CHAMU |
| Sewer availability | Cleared | 2/22/2024 | ARNULFO CHAMU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Muller,, Paul; Lic. No.: C83707 | 338 VIEWPARK CIRCLE SAN JOSE, CA 95136 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/22/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 10/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/23/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Sewer | 10/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Underground Mechanical | 10/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 10/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/14/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/14/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 11/14/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/14/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/22/2024 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/26/2024 | Corrections Issued | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 12/11/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/11/2024 | Approved | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 12/11/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 12/17/2024 | Approved | SEAN HAUPT |
| Insulation | 12/17/2024 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 12/24/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 12/30/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/30/2024 | Approved | SEAN HAUPT |
| Shower Pan | 12/30/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/3/2025 | Approved | SEAN HAUPT |
| Sewer | 1/24/2025 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 1/24/2025 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 3/17/2025 | Approved | ARAM AVEDISIAN |
| Final | 3/17/2025 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2025 | SGSOV Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 3/17/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/8/2025 | Approved | EVAN COOPER |
| Final | 4/8/2025 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 4/8/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/8/2025 | Approved | EVAN COOPER |