972 S HILGARD AVE 90024

Certificate Information: 972 S HILGARD AVE 90024

Application / Permit
23016-10000-37798
Plan Check / Job No.
B23LA20376
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePLAN. EXTERIOR ALTERATION TO (E) APARTMENT. REMOVE AND REPLACE GUARDS. REMOVE PORTION OF (E) BALCONY OF THIRD FLOOR.
Permit Issued
Issued on 4/25/2024
Issuing Office
Current Status
Permit Finaled on 6/16/2025

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/2/2023 KEVIN MORALES
Assigned to Zoning Architect 11/2/2023 SARHAD GHEVANDIAN
Corrections Issued 11/6/2023 KEVIN MORALES
Quality Review Completed 11/7/2023 EUGENE BARBEAU
Applicant returned to address corrections 12/12/2023 KEVIN MORALES
Plan Check Approved 12/21/2023 KEVIN MORALES
Issued 4/25/2024 APPLICANT
Permit Finaled 6/16/2025 RICARDO ROBLES

Permit Application Clearance Information

"Q" conditions Cleared 11/16/2023 KEVIN FULTON
Specific Plan Cleared 11/16/2023 KEVIN FULTON
Specific Plan Cleared 11/16/2023 KEVIN FULTON
Zoning Plan Check Cleared 12/19/2023 Hernan Arreola

Contact Information

Contractor Aggregate Construction Group; Lic. No.: 1034714-B       ,
Contractor Aggregate Real Estate Solutions; Lic. No.: 1034714-B       ,

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2024 Approved PAUL DAVIDSON
Deputy Drilled-In Anchors 9/26/2024 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 9/26/2024 Conditional Approval DANIEL VARNUM
Wood Frame 10/15/2024 Corrections Issued DANIEL VARNUM
Interior/Exterior Lathing 12/19/2024 Not Ready for Inspection RICARDO ROBLES
Interior/Exterior Lathing 12/20/2024 Approved DANIEL VARNUM
Wood Frame 12/20/2024 Approved DANIEL VARNUM
Final 3/27/2025 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 3/27/2025 Not Ready for Inspection DANIEL VARNUM
Final 6/10/2025 Not Ready for Inspection RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Not Ready RICARDO ROBLES
Smoke Detectors 6/10/2025 Not Ready for Inspection RICARDO ROBLES
Pre-Inspection 6/11/2025 Approved RICARDO ROBLES
Final 6/16/2025 Permit Finaled RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Approved RICARDO ROBLES
Smoke Detectors 6/16/2025 Approved RICARDO ROBLES