1038 E NOWITA PL 90291

Certificate Information: 1038 E NOWITA PL 90291

Application / Permit
23016-10000-37745
Plan Check / Job No.
B23LA20348
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO ACCESSORY DWELLING UNIT PER STATE LAW COMPLY WITH DEPARTMENT ORDER effective date 08/28/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case #989794.
Permit Issued
Issued on 5/7/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2023 APPLICANT
Assigned to Plan Check Engineer 10/26/2023 DANIEL SANJUAN
Corrections Issued 10/26/2023 DANIEL SANJUAN
Applicant returned to address corrections 1/12/2024 FERNANDO FLORES
Plan Check Approved 1/19/2024 GEORGE ALVAREZ
Plan Check Approved 1/19/2024 ALEXANDER JOO
Issued 5/7/2024 APPLICANT
CofO in Progress 11/6/2024 JOHN MATTILLO
Permit Finaled 4/24/2025 CLAUDIO MORENO
CofO Issued 4/24/2025 CLAUDIO MORENO
Permit Finaled 4/24/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 11/15/2023 LIAM ODONOVAN
Sewer availability Cleared 11/15/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 11/17/2023 LIAM ODONOVAN
Specific Plan Cleared 11/29/2023 JOSHUA JONES
Roof/Waste drainage to street Cleared 1/8/2024 BRENDEN HAWK

Contact Information

Contractor Paradigm Home Builders Inc; Lic. No.: 1100775-B 1800 CENTURY PARK EAST   SUITE 600    LOS ANGELES, CA 90067

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/22/2024 Conditional Approval JOHN MATTILLO
Footing/Foundation/Slab 5/29/2024 Approved RYAN BARNES
Pre-Inspection 6/17/2024 Not Ready for Inspection RYAN BARNES
Pre-Inspection 6/18/2024 Not Ready for Inspection RYAN BARNES
Pre-Inspection 6/21/2024 Not Ready for Inspection RYAN BARNES
Excavation/Setback/Form/Re-Bar 6/25/2024 Conditional Approval RYAN BARNES
Wood Frame 7/16/2024 Approved RYAN BARNES
Insulation 7/23/2024 Approved JOHN MATTILLO
Interior/Exterior Lathing 7/23/2024 Approved JOHN MATTILLO
Drywall Nailing 7/29/2024 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Not Ready RYAN BARNES
Final 9/5/2024 OK to Issue CofO RYAN BARNES
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Approved RYAN BARNES
Smoke Detectors 9/5/2024 Approved RYAN BARNES