6508 W 84TH PL 90045
Certificate Information: 6508 W 84TH PL 90045
- Application / Permit
- 23016-10000-37618
- Plan Check / Job No.
- B23LA20268
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Detached 20' X 20' Garage to (N) ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/26/2023
- Issuing Office
- Current Status
- CofO Issued on 4/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2023 | AMY GUEVARRA |
| Corrections Issued | 11/6/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 12/7/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/13/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/18/2023 | EDWIN ESPIN |
| Plan Check Approved | 12/20/2023 | GURUNATH NESARAJAH |
| No Progress | 12/20/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/20/2023 | GURUNATH NESARAJAH |
| Issued | 12/26/2023 | APPLICANT |
| CofO in Progress | 4/19/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 4/22/2024 | DANIEL ORRANTE |
| CofO Issued | 4/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2023 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2023 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 12/1/2023 | MOHAMMAD HASAN |
| Sewer availability | Cleared | 12/18/2023 | BRENDEN HAWK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Kunyoung; Lic. No.: C66880 | 22812 ERIEL AVE TORRANCE, CA 90505 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/17/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Deputy Wood Construction | 1/19/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 1/30/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Sewer | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 2/8/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/20/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Green Building Rough | 2/20/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 2/28/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 3/4/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 3/15/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 3/15/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 3/15/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 4/3/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/4/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/4/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 4/4/2024 | Approved | TEMISTOCLES CAAL |
| Final | 4/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 4/15/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 4/15/2024 | Approved | TEMISTOCLES CAAL |
| Final | 4/18/2024 | OK to Issue CofO | TEMISTOCLES CAAL |