1071 S QUEEN ANNE PL 90019
Certificate Information: 1071 S QUEEN ANNE PL 90019
- Application / Permit
- 23016-10000-37554
- Plan Check / Job No.
- B23LA20215
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK TO BE DONE PER ARCHITECT DESIGN.
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Current Status
- CofO Issued on 1/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2023 | MADISON ODELL |
| Corrections Issued | 10/28/2023 | MADISON ODELL |
| Applicant returned to address corrections | 11/11/2023 | MADISON ODELL |
| Plan Check Approved | 3/3/2024 | MADISON O'DELL |
| Issued | 4/2/2024 | APPLICANT |
| CofO in Progress | 1/21/2025 | JUSTIN HAWLEY |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
| CofO Issued | 1/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 11/1/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2023 | JUSTIN BICOL |
| Construction near power lines | Cleared | 2/21/2024 | RIDWAN HARDY |
Contact Information
| Architect | Chang,, Eric Cheng-Che; Lic. No.: NA25031 | , |
| Contractor | Nucon Group Inc; Lic. No.: 748689-B | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/12/2024 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 4/12/2024 | Partial Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 5/22/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 5/22/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Underground Mechanical | 5/22/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 6/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 6/5/2024 | Partial Approval | JUSTIN HAWLEY |
| Underground Mechanical | 6/5/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/7/2024 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 6/7/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | JUSTIN HAWLEY |
| Shower Pan | 6/18/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 6/24/2024 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 6/26/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 7/1/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 7/1/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/1/2024 | Approved | JUSTIN HAWLEY |
| Final | 8/1/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 8/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 8/1/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 8/2/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 8/2/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 8/2/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 8/2/2024 | Approved | JUSTIN HAWLEY |
| Final | 1/21/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 1/21/2025 | Approved | JUSTIN HAWLEY |