1071 S QUEEN ANNE PL 90019

Certificate Information: 1071 S QUEEN ANNE PL 90019

Application / Permit
23016-10000-37554
Plan Check / Job No.
B23LA20215
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK TO BE DONE PER ARCHITECT DESIGN.
Permit Issued
Issued on 4/2/2024
Issuing Office
Current Status
CofO Issued on 1/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2023 APPLICANT
Assigned to Plan Check Engineer 10/27/2023 MADISON ODELL
Corrections Issued 10/28/2023 MADISON ODELL
Applicant returned to address corrections 11/11/2023 MADISON ODELL
Plan Check Approved 3/3/2024 MADISON O'DELL
Issued 4/2/2024 APPLICANT
CofO in Progress 1/21/2025 JUSTIN HAWLEY
Permit Finaled 1/26/2025 DEROLD HAUFF
Permit Finaled 1/26/2025 DEROLD HAUFF
CofO Issued 1/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2023 JUSTIN BICOL
Sewer availability Cleared 11/1/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 11/8/2023 JUSTIN BICOL
Construction near power lines Cleared 2/21/2024 RIDWAN HARDY

Contact Information

Architect Chang,, Eric Cheng-Che; Lic. No.: NA25031       ,
Contractor Nucon Group Inc; Lic. No.: 748689-B       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2024 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 4/12/2024 Partial Approval JUSTIN HAWLEY
Footing/Foundation/Slab 5/22/2024 Approved JUSTIN HAWLEY
HVAC-Rough 5/22/2024 Not Ready for Inspection JUSTIN HAWLEY
Underground Mechanical 5/22/2024 Approved JUSTIN HAWLEY
Green Building Rough 6/5/2024 Not Ready for Inspection JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 6/5/2024 Partial Approval JUSTIN HAWLEY
Underground Mechanical 6/5/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 6/7/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 6/7/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 6/18/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/18/2024 Partial Approval JUSTIN HAWLEY
Shower Pan 6/18/2024 Approved JUSTIN HAWLEY
Insulation 6/24/2024 Corrections Issued RONNIE MINDANAO
Insulation 6/26/2024 Approved JUSTIN HAWLEY
Drywall Nailing 7/1/2024 Approved JUSTIN HAWLEY
Green Building Rough 7/1/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 7/1/2024 Approved JUSTIN HAWLEY
Final 8/1/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 8/1/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Not Required JUSTIN HAWLEY
Smoke Detectors 8/1/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 8/2/2024 Approved JUSTIN HAWLEY
HVAC-Final 8/2/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 8/2/2024 Approved JUSTIN HAWLEY
Service/Power Release 8/2/2024 Approved JUSTIN HAWLEY
Final 1/21/2025 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 1/21/2025 Approved JUSTIN HAWLEY