727 N VINE ST 90038

Certificate Information: 727 N VINE ST 90038

Application / Permit
23016-10000-37498
Plan Check / Job No.
B23LA20183
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Tenant improvement of existing market with storage racks ( < 8 ft high)
Permit Issued
Issued on 4/18/2024
Issuing Office
Current Status
Permit Finaled on 7/29/2025

Permit Application Status History

Submitted 10/26/2023 APPLICANT
Assigned to Plan Check Engineer 11/2/2023 TSE MING HUANG
Corrections Issued 11/6/2023 TSE MING HUANG
Quality Review Completed 11/6/2023 EUGENE BARBEAU
Plan Check Approved 2/13/2024 TSE MING HUANG
Issued 4/18/2024 APPLICANT
Permit Finaled 7/28/2025 TIMOTHY POWELL

Permit Application Clearance Information

Sewer availability Cleared 11/18/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/20/2023 TREVOR QUAN
Green Code Cleared 12/14/2023 MICHAEL AYERS
DAS Clearance Cleared 12/18/2023 Hernan Arreola
Food Service Establishment Cleared 1/30/2024 KENNETH BROWNE
Food establishment approval Cleared 2/12/2024 LACDHS APPROVED

Contact Information

Architect Craig,, J Cedric; Lic. No.: NA15490       ,
Contractor Harco Group Inc; Lic. No.: 842851-B       ,
Contractor Mal-Wal Of Southern California Inc; Lic. No.: 842851-B       ,
Engineer Hardin,, Douglas; Lic. No.: C85243 3803 SOUTH GEMINI CIRCLE      BOISE, ID 83709

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 5/2/2024 Partial Inspection TIMOTHY POWELL
Wood Frame 5/13/2024 No Access for Inspection EDWIN GREGORYONA
Wood Frame 5/14/2024 Approved RONALD JIMENEZ
Light Gage Steel Frame 5/17/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 5/20/2024 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 5/20/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 5/21/2024 Not Ready for Inspection TIMOTHY POWELL
Light Gage Steel Frame 5/21/2024 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 5/24/2024 Partial Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 7/22/2024 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 7/25/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 8/5/2024 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 9/16/2024 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 9/26/2024 Conditional Approval DARRYL ARNOLD
Light Gage Steel Frame 10/3/2024 Partial Approval TIMOTHY POWELL
Final 2/12/2025 Partial Inspection TIMOTHY POWELL
Green Building Final 2/12/2025 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Approved TIMOTHY POWELL
Smoke Detectors 2/12/2025 Approved TIMOTHY POWELL
Final 6/27/2025 Corrections Issued DARRYL ARNOLD
Green Building Final 6/27/2025 Conditional Approval DARRYL ARNOLD
Final 7/28/2025 Permit Finaled TIMOTHY POWELL
Green Building Final 7/28/2025 Approved TIMOTHY POWELL