3380-3380 1/2 W HAMILTON WAY 90026
Certificate Information: 3380-3380 1/2 W HAMILTON WAY 90026
- Application / Permit
- 23016-10000-37078
- Plan Check / Job No.
- B23LA19970
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGETO TWO UNIT ATTACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- Current Status
- CofO Issued on 7/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2023 | DANIEL YIP |
| Corrections Issued | 11/4/2023 | DANIEL YIP |
| Quality Review Completed | 11/7/2023 | GARO TELMI |
| Applicant returned to address corrections | 1/29/2024 | DANIEL YIP |
| Plan Check Approved | 2/29/2024 | DANIEL YIP |
| Issued | 2/29/2024 | APPLICANT |
| CofO in Progress | 7/11/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
| CofO Issued | 7/13/2025 | DEROLD HAUFF |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 12/5/2023 | ARNULFO CHAMU |
| Grading Pre-Inspection | Cleared | 12/28/2023 | CHARLES POWELL |
| Construction near power lines | Cleared | 1/19/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/19/2024 | RIDWAN HARDY |
| DAS Clearance | Cleared | 2/28/2024 | ELIZABETH TOMS |
Contact Information
| Contractor | Rolenconstruction Llc; Lic. No.: 1105889-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2024 | Corrections Issued | ROY SPAULDING |
| Pre-Inspection | 5/9/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/19/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/26/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 11/22/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/22/2024 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/26/2024 | Approved | LUIS CASTRO |
| Gas Test | 11/26/2024 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 11/26/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/9/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/9/2024 | Approved | HAMIK HARTOUNIAN |
| Insulation | 12/12/2024 | No Access for Inspection | JOSH MEISTER |
| Insulation | 12/13/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 12/23/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/30/2024 | Approved | WILLIAM SIERRA |
| Shower Pan | 1/10/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/15/2025 | Approved | ANTHONY RAMOS |
| Sewer | 1/22/2025 | Approved | JOSH MEISTER |
| Underground Mechanical | 4/30/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 6/27/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/27/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 7/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 7/11/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 7/11/2025 | Approved | HAMIK HARTOUNIAN |