4029 S BEETHOVEN ST 90066

Certificate Information: 4029 S BEETHOVEN ST 90066

Application / Permit
23016-10000-37064
Plan Check / Job No.
B23LA18912
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - CONVERT EXISTING GARAGE TO ADU PER 12.22 A33 C & D
Permit Issued
Issued on 4/3/2024
Issuing Office
Current Status
CofO Issued on 2/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 STARR CHEN
Plan Check Approved 4/3/2024 STARR CHEN
No Progress 4/3/2024 STARR CHEN
Plan Check Approved 4/3/2024 STARR CHEN
Issued 4/3/2024 APPLICANT
Permit Closed-Status Void 5/30/2024 JESUS RODRIGUEZ
Re-Activate Permit 7/1/2024 JESUS RODRIGUEZ
CofO in Progress 2/20/2025 JESUS PINEDA
CofO in Progress 2/20/2025 JESUS PINEDA
CofO in Progress 2/21/2025 JESUS PINEDA
Permit Finaled 2/21/2025 RICHARD STEINBACH
CofO Issued 2/21/2025 RICHARD STEINBACH
Permit Finaled 2/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/25/2023 DARIN LAM
Roof/Waste drainage to street Cleared 10/25/2023 DARIN LAM
Sewer availability Cleared 10/25/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 10/26/2023 DARIN LAM
Specific Plan Cleared 11/7/2023 FREDDY GARCIA
Construction near power lines Cleared 2/8/2024 RIDWAN HARDY
Construction within easement Cleared 2/8/2024 RIDWAN HARDY

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: C22676 2155 VERDUGO BLVD # 330      MONTROSE, CA 91020
Contractor Adar Builders Inc; Lic. No.: 1051859-B       ,
Engineer Kennedy,, Nicholas; Lic. No.: S6884 3664 FENWAY STREET      FOREST GROVE, OR 97116

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 4/9/2024 Partial Approval JESUS RODRIGUEZ
Final 5/30/2024 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 7/9/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 7/9/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/12/2024 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 7/26/2024 Approved REGINA MENDEZ
Special/Order Compliance 7/26/2024 Approved JESUS RODRIGUEZ
Insulation 7/30/2024 Approved SEAN HAUPT
Drywall Nailing 8/14/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/2/2024 Not Ready for Inspection JESUS PINEDA
Final 12/2/2024 Corrections Issued JESUS PINEDA
Green Building Final 12/2/2024 Not Ready for Inspection JESUS PINEDA
Green Building Rough 12/2/2024 Not Ready for Inspection JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 12/2/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 12/3/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 12/31/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Final 12/31/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 12/31/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 1/6/2025 Approved JESUS PINEDA
HVAC-Final 1/6/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 1/6/2025 Corrections Issued JESUS PINEDA
Service/Power Release 1/6/2025 Not Ready for Inspection JESUS PINEDA
Pre-Inspection 2/7/2025 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 2/11/2025 Approved JESUS PINEDA
Final 2/11/2025 Not Ready for Inspection JESUS PINEDA
Green Building Final 2/11/2025 Approved JESUS PINEDA
Green Building Rough 2/11/2025 Approved JESUS PINEDA
HVAC-Final 2/11/2025 Approved JESUS PINEDA
PLUMBING-Final 2/11/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 2/11/2025 Approved JESUS PINEDA
ELECTRICAL-Final 2/19/2025 Approved JESUS PINEDA
Final 2/19/2025 Not Ready for Inspection JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Approved JESUS PINEDA
Special/Order Compliance 2/20/2025 Corrections Issued JESUS PINEDA
Final 2/21/2025 OK to Issue CofO JESUS PINEDA