1507 E 109TH ST 90059

Certificate Information: 1507 E 109TH ST 90059

Application / Permit
23016-10000-36942
Plan Check / Job No.
B23LA19852
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN Convert Part of Existing Unit into New Rec. Room on (E) DUPLEX and Add New Covered Patio ( 14.42ft x 14 ft). See Comment.
Permit Issued
Issued on 6/6/2024
Issuing Office
Current Status
CofO in Progress on 5/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/23/2023 APPLICANT
Assigned to Plan Check Engineer 10/25/2023 TSE MING HUANG
Corrections Issued 10/30/2023 TSE MING HUANG
Quality Review Completed 11/1/2023 EUGENE BARBEAU
Applicant returned to address corrections 4/3/2024 TSE MING HUANG
Plan Check Approved 4/18/2024 TSE MING HUANG
Issued 6/6/2024 APPLICANT
CofO in Progress 5/13/2026 ARTHUR NEGRETE

Permit Application Clearance Information

Sewer availability Cleared 11/30/2023 AMBER CAMPBELL
Tenant Habitability Plan Cleared 12/1/2023 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 12/12/2023 AMBER CAMPBELL

Contact Information

Contractor Leslie Electric Co; Lic. No.: 936228-B       ,
Engineer Herrera,, Edgar E; Lic. No.: C67603 1929 GREENLEAF DR      WEST COVINA, CA 91792

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2025 Partial Inspection ANTHONY EGSON
BUILDING-Rough-Frame 10/30/2025 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 10/30/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 10/30/2025 Approved ANTHONY EGSON
HVAC-Rough 10/30/2025 Approved ANTHONY EGSON
Insulation 10/30/2025 Approved ANTHONY EGSON
PLUMBING-Rough 10/30/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/13/2025 Approved ANTHONY EGSON
Drywall Nailing 11/13/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/18/2025 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 12/2/2025 Approved ARTHUR NEGRETE
Final 12/2/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 12/2/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 12/2/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 12/2/2025 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 12/2/2025 Approved ARTHUR NEGRETE
Final 5/12/2026 OK to Issue CofO ARTHUR NEGRETE