6801 W HOLLYWOOD BLVD 90028
Certificate Information: 6801 W HOLLYWOOD BLVD 90028
- Application / Permit
- 23016-10000-36930
- Plan Check / Job No.
- B23LA19839
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- TI to existing Take out Restaurant.
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/7/2024
Permit Application Status History
| Submitted | 10/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/19/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 1/23/2024 | SALVADOR QUINTANILLA |
| Issued | 1/26/2024 | APPLICANT |
| Permit Finaled | 6/7/2024 | TIMOTHY POWELL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 11/7/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 11/14/2023 | DAVID URITA |
| Food establishment approval | Cleared | 12/11/2023 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 1/12/2024 | PAWAN VERMA |
Contact Information
| Contractor | Calasia Construction Inc; Lic. No.: 938255-B | 3050 FLETCHER DRIVE LOS ANGELES, CA 90065 |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 3/12/2024 | Partial Approval | JACOB MYERS |
| Light Gage Steel Frame | 3/12/2024 | Partial Approval | JACOB MYERS |
| Drywall Nailing | 3/14/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 4/19/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 4/19/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 4/25/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Interior/Exterior Lathing | 5/2/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 5/2/2024 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 5/8/2024 | Approved | TIMOTHY POWELL |
| Pre-Inspection | 5/17/2024 | Partial Inspection | TIMOTHY POWELL |
| Final | 6/4/2024 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | TIMOTHY POWELL |
| Smoke Detectors | 6/4/2024 | Approved | TIMOTHY POWELL |
| Final | 6/7/2024 | Permit Finaled | TIMOTHY POWELL |