12430 W SHORT AVE 90066

Certificate Information: 12430 W SHORT AVE 90066

Application / Permit
23016-10000-36926
Plan Check / Job No.
B23LA19837
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Exterior and interior alteration of existing 1-story single family dwelling. Work per WFPP. **ePLAN**
Permit Issued
Issued on 4/15/2024
Issuing Office
Current Status
Issued on 4/15/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2023 APPLICANT
Assigned to Plan Check Engineer 10/24/2023 VICTOR CHEN
Plan Check Approved 10/27/2023 VICTOR CHEN
Refund in Progress 1/29/2024 SELENIA GARCIA
Refund Closed 1/29/2024 SELENIA GARCIA
Issued 4/15/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Dotz Inc; Lic. No.: 1033830-B       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/10/2026   
Smoke Detectors 6/10/2026   
SGSOV-Seismic Gas S/O Valve 6/10/2026   

Inspection Request History

Footing/Foundation/Slab 4/22/2024 Corrections Issued TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 4/24/2024 No Access for Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 4/25/2024 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 6/7/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 6/7/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Corrections Issued TEMISTOCLES CAAL
Interior/Exterior Lathing 12/16/2024 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 12/20/2024 Partial Approval MICHAEL ALLEN
Insulation 1/7/2025 Approved MICHAEL ALLEN
Special/Order Compliance 1/7/2025 Corrections Issued MICHAEL ALLEN
Drywall Nailing 1/27/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 1/27/2025 Approved MICHAEL ALLEN
Shower Pan 2/21/2025 Approved MICHAEL ALLEN
Drywall Nailing 3/4/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/4/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/7/2025 Approved MICHAEL ALLEN
Special/Order Compliance 3/7/2025 Corrections Issued MICHAEL ALLEN
Special/Order Compliance 3/7/2025 Partial Approval RUBEN RIVAS
Reinforced Concrete Frame 3/11/2025 Corrections Issued RUBEN RIVAS
Special/Order Compliance 3/11/2025 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 3/17/2025 Corrections Issued RUBEN RIVAS
Special/Order Compliance 3/17/2025 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 4/7/2025 Corrections Issued RUBEN RIVAS
Wood Frame 4/7/2025 Corrections Issued RUBEN RIVAS
Reinforced Concrete Frame 4/21/2025 Approved RUBEN RIVAS
Wood Frame 4/21/2025 Approved RUBEN RIVAS