4356 N LAUREL CANYON BLVD 91604
Certificate Information: 4356 N LAUREL CANYON BLVD 91604
- Application / Permit
- 23016-10000-36768
- Plan Check / Job No.
- B23LA19731
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- Change of use from (E) retial to nail salon
- Permit Issued
- Issued on 11/20/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2023 | SHANGQIN XIE |
| Corrections Issued | 10/24/2023 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/1/2023 | SHANGQIN XIE |
| Plan Check Approved | 11/7/2023 | SHANGQIN XIE |
| Issued | 11/20/2023 | APPLICANT |
| CofO in Progress | 3/26/2024 | ANDREW DORSO |
| Permit Finaled | 3/26/2024 | JEFFREY DURAN |
| CofO Issued | 3/26/2024 | JEFFREY DURAN |
| Permit Finaled | 3/26/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/1/2023 | COLIN LOREDO |
| "Q" conditions | Cleared | 11/2/2023 | BRENNEN OBETO |
| Comm Cor/Mini-Mall | Cleared | 11/2/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 11/2/2023 | BRENNEN OBETO |
Contact Information
| Contractor | Abrahamyan Levon; Lic. No.: 1104463-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/1/2023 | Corrections Issued | ROBERT DAVIS |
| Wood Frame | 12/1/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 1/3/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 1/4/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 1/5/2024 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 1/9/2024 | Approved | ROBERT DAVIS |
| T-Bar Ceiling | 1/26/2024 | Corrections Issued | ROBERT DAVIS |
| T-Bar Ceiling | 1/30/2024 | Approved | ROBERT DAVIS |
| Final | 3/15/2024 | Not Ready for Inspection | ANDREW DORSO |
| Smoke Detectors | 3/15/2024 | Corrections Issued | ANDREW DORSO |
| Final | 3/21/2024 | OK to Issue CofO | ANDREW DORSO |
| Smoke Detectors | 3/21/2024 | Approved | ANDREW DORSO |