5500 W 98TH ST 90045

Certificate Information: 5500 W 98TH ST 90045

Application / Permit
23016-10000-36592
Plan Check / Job No.
B23LA19612
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
ePlan, LAX. 1st time TI for Sixt Rent-A-Car at LAX Rent-A-Car Center (Conrac) Level 1: Ready/Return and Idle Storage Operations Level 5: Customer Service Building
Permit Issued
Issued on 8/29/2024
Issuing Office
Current Status
Issued on 8/29/2024

Permit Application Status History

Submitted 10/31/2023 APPLICANT
Assigned to Plan Check Engineer 11/1/2023 FARSHAD ALIMOHAMADI
Corrections Issued 11/6/2023 FARSHAD ALIMOHAMADI
Quality Review Completed 11/7/2023 LIPING TENG
Applicant returned to address corrections 6/4/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 8/13/2024 FARSHAD ALIMOHAMADI
Issued 8/29/2024 APPLICANT

Permit Application Clearance Information

Project Permit Cleared 12/21/2023 MERCEDES ORTIZ
Airport buildings Cleared 2/2/2024 ANDREW KO
Green Code Cleared 2/8/2024 AARON COSTA
DAS Clearance Cleared 3/10/2024 ELIZABETH TOMS
City owned building/parcel Cleared 3/29/2024 FARSHAD ALIMOHAMADI

Contact Information

Architect Gerber,, Jeffrey P; Lic. No.: C27945 14 ESTANCIA PLACE      THE WOODLANDS, TX 77309
Contractor J D K Llc; Lic. No.: 1119568-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 6/12/2025 Not Ready for Inspection NICK LAROCCA
Wood Frame 6/13/2025 Corrections Issued NICK LAROCCA
Final 11/14/2025 Not Ready for Inspection RICARDO ROBLES
Green Building Final 11/14/2025 Not Ready for Inspection RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Not Ready RICARDO ROBLES
Smoke Detectors 11/14/2025 Not Ready for Inspection RICARDO ROBLES
T-Bar Ceiling 2/18/2026 Not Ready for Inspection NICK LAROCCA
T-Bar Ceiling 2/23/2026 Approved VASIL MIHALEV
Pre-Inspection 2/27/2026 Approved NICK LAROCCA
Final 3/5/2026 Not Ready for Inspection NICK LAROCCA
Green Building Final 3/5/2026 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved NICK LAROCCA
Smoke Detectors 3/5/2026 Approved NICK LAROCCA
Final 3/9/2026 Not Ready for Inspection NICK LAROCCA
Final 5/1/2026 Not Ready for Inspection MICHAEL PETRUSKO