680 W 16TH ST 90731
Certificate Information: 680 W 16TH ST 90731
- Application / Permit
- 23016-10000-36495
- Plan Check / Job No.
- B23LA19556
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install New Wood shear wall at 1st floor garage area to comply with Soft Story ordinance. Separate permit was obtained under permit 23014-10000-03279 to build a new ADU addition over existing first floor garage. Propose ADU addition is attached to existing apartment building on second floor.
- Permit Issued
- Issued on 4/24/2024
- Issuing Office
- Current Status
- CofC Issued on 11/12/2025
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | HANS SANTIAGO |
| Corrections Issued | 10/30/2023 | HANS SANTIAGO |
| Quality Review Completed | 11/13/2023 | CHARMIE HUYNH |
| Applicant returned to address corrections | 12/12/2023 | HANS SANTIAGO |
| Plan Check Approved | 1/19/2024 | ANDREW SANTIAGO |
| Issued | 4/24/2024 | APPLICANT |
| OK for CofC | 11/6/2025 | DARRYL ARNOLD |
| CofC Issued | 11/12/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/4/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Mg Elite Construction; Lic. No.: 1098511-B | 400 N VALENCIA ST LA HABRA, CA 90631 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/24/2024 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 7/30/2024 | Partial Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 8/20/2024 | Partial Inspection | AMANUEL BERHE |
| Deputy Drilled-In Anchors | 9/27/2024 | Conditional Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/27/2024 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 1/21/2025 | Corrections Issued | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 8/4/2025 | Corrections Issued | MICHAEL PETRUSKO |
| Wood Frame | 8/5/2025 | Corrections Issued | MICHAEL PETRUSKO |
| Insulation | 8/7/2025 | Approved | RICARDO ROBLES |
| Drywall Nailing | 8/13/2025 | Approved | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Conditional Approval | MICHAEL PETRUSKO |
| Interior/Exterior Lathing | 8/28/2025 | Approved | RICARDO ROBLES |
| Final | 9/23/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 9/23/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 10/7/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 10/7/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 10/14/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 10/14/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 10/17/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 10/17/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 11/6/2025 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 11/6/2025 | Approved | DARRYL ARNOLD |