1927 N AVENUE 51 90042
Certificate Information: 1927 N AVENUE 51 90042
- Application / Permit
- 23016-10000-36493
- Plan Check / Job No.
- B23LA19554
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Partial Conversion of (E) Dettached Garage to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/4/2024
- Issuing Office
- Current Status
- CofO Issued on 8/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2023 | ALFREDO JARA |
| Corrections Issued | 10/23/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 1/30/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/24/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 4/25/2024 | EDWIN ESPIN |
| Plan Check Approved | 4/26/2024 | EDWIN ESPIN |
| Issued | 5/4/2024 | APPLICANT |
| CofO in Progress | 8/19/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 8/22/2025 | DEROLD HAUFF |
| CofO Issued | 8/22/2025 | DEROLD HAUFF |
| Permit Finaled | 8/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2023 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 10/25/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/25/2023 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 1/4/2024 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | JUSTIN BICOL |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/21/2024 | Partial Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 8/21/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 8/21/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/21/2024 | Corrections Issued | CRAIG VAUGHAN |
| Wood Frame | 8/21/2024 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 8/23/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 10/15/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/29/2024 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 11/27/2024 | Corrections Issued | ROY SPAULDING |
| Shower Pan | 12/11/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 12/31/2024 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 5/2/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 5/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 5/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 5/2/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | DAVID WILLIAMS |
| Final | 5/9/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 5/9/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 5/9/2025 | Approved | DAVID WILLIAMS |
| Final | 8/19/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |