4345-4345 1/2 E MONT EAGLE PL 90041
Certificate Information: 4345-4345 1/2 E MONT EAGLE PL 90041
- Application / Permit
- 23016-10000-36333
- Plan Check / Job No.
- B23LA19482
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) CRAWL SPACE OF (E) TWO STORY SFD INTO HABITABLE SPACE AND INTO AN ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Current Status
- Issued on 4/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 11/3/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 11/14/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/16/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/1/2024 | SERGIO GUTIERREZ |
| Issued | 4/2/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 12/19/2023 | ROBERT HUGHES |
| Roof/Waste drainage to street | Cleared | 12/19/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/19/2023 | ADRIAN SANCHEZ |
| Street Frontage | Cleared | 12/19/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 2/2/2024 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bermejo,, Gil Banzon; Lic. No.: C86264 | 2308 MOUNTAIN OAK RD BAKERSFIELD, CA 93311 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/23/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 4/23/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/23/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 4/23/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 5/14/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 6/7/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/28/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 9/10/2024 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Rough | 5/7/2025 | Approved | NICHOLAS LOPEZ |
| Pre-Inspection | 5/7/2025 | Partial Inspection | NICHOLAS LOPEZ |
| Wood Frame | 5/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 5/13/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 5/29/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 5/29/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 5/29/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 5/29/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 6/3/2025 | Approved | NICHOLAS LOPEZ |