2418 1/2 N MORENO DR 90039
Certificate Information: 2418 1/2 N MORENO DR 90039
- Application / Permit
- 23016-10000-36290
- Plan Check / Job No.
- B23LA19458
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT STATE LAW PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/19/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/6/2023 | MINA HABILI |
| Issued | 12/6/2023 | APPLICANT |
| CofO in Progress | 1/27/2025 | JOSE MACIAS |
| Permit Finaled | 2/20/2025 | DEROLD HAUFF |
| CofO Issued | 2/20/2025 | DEROLD HAUFF |
| Permit Finaled | 2/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 10/24/2023 | ARNULFO CHAMU |
| Hydrant and Access approval | Cleared | 12/5/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| CRAIG DAVIS, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| AMIR NAZARIAN, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| GEM DE OCAMPO, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| DEVON JACKSON, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSH MEISTER, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANTHONY RAMOS, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| KELVIN MARTINEZ, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER MORFIN, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MAGCALAS, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEX COLIN, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT FINNILA, (213) 216-1123 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Pre-Inspection | 12/12/2023 | Approved | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Corrections Issued | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 12/28/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2023 | Partial Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 1/5/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 1/30/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 1/30/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/5/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/4/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 6/4/2024 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/4/2024 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/4/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/6/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/6/2024 | Partial Approval | ENRIQUE MIRELES |
| Insulation | 6/10/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Corrections Issued | JEFFREY MEAD |
| Drywall Nailing | 6/14/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/24/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/24/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/24/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 6/24/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/20/2024 | Corrections Issued | JOSE MACIAS |
| Final | 12/20/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 12/20/2024 | Approved | JOSE MACIAS |
| HVAC-Final | 12/20/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 12/20/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 12/20/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 12/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 12/23/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 1/23/2025 | Approved | JOSE MACIAS |
| Final | 1/23/2025 | OK to Issue CofO | JOSE MACIAS |
| Gas Test | 1/23/2025 | Approved | JOSE MACIAS |