5742 W FALLSGROVE ST 90016
Certificate Information: 5742 W FALLSGROVE ST 90016
- Application / Permit
- 23016-10000-35862
- Plan Check / Job No.
- B23LA19294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSING (E) COVERED FRONT PATIO AND REAR PORCH AND ADDITION TO THE REAR OF (E) SFD
- Permit Issued
- Issued on 11/16/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | LUKE GONZALES |
| Corrections Issued | 10/13/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 10/25/2023 | MINA HABILI |
| Plan Check Approved | 11/16/2023 | LUKE GONZALES |
| Issued | 11/16/2023 | APPLICANT |
| CofO in Progress | 6/7/2024 | ANTHONY EGSON |
| CofO Issued | 6/10/2024 | DEROLD HAUFF |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/18/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | AMBER CAMPBELL |
| Grading Pre-Inspection | Cleared | 10/25/2023 | LUKE GONZALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/12/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/18/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 12/18/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 12/18/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2023 | Partial Approval | SABAS ALONSO |
| Wood Frame | 12/21/2023 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Wood Construction | 12/28/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/17/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 1/17/2024 | Corrections Issued | ANTHONY EGSON |
| Insulation | 1/22/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/22/2024 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 1/22/2024 | Approved | ANTHONY EGSON |
| Insulation | 1/25/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/29/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 1/29/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 1/29/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/30/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 1/30/2024 | Approved | ANTHONY EGSON |
| Sewer | 3/8/2024 | No Access for Inspection | ANTHONY EGSON |
| Sewer | 3/12/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/16/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/16/2024 | Approved | ANTHONY EGSON |
| Final | 4/16/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 4/16/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 4/16/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/16/2024 | Approved | ANTHONY EGSON |
| Final | 4/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/28/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 5/28/2024 | Approved | ANTHONY EGSON |
| Final | 6/6/2024 | OK to Issue CofO | ANTHONY EGSON |
| PLUMBING-Final | 6/6/2024 | Approved | ANTHONY EGSON |
| Service/Power Release | 6/7/2024 | Approved | ANTHONY EGSON |