6822 N CHIMINEAS AVE 91335
Certificate Information: 6822 N CHIMINEAS AVE 91335
- Application / Permit
- 23016-10000-35793
- Plan Check / Job No.
- B23LA19265
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE AND (N) 25' X 26'4" ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/4/2024
- Issuing Office
- Current Status
- CofO Issued on 2/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2023 | MADISON ODELL |
| Corrections Issued | 10/18/2023 | MADISON ODELL |
| Applicant returned to address corrections | 11/14/2023 | MADISON ODELL |
| Applicant returned to address corrections | 12/5/2023 | MADISON ODELL |
| Plan Check Approved | 3/1/2024 | MADISON O'DELL |
| Issued | 3/4/2024 | APPLICANT |
| CofO in Progress | 2/3/2025 | ARUTYUN MADATYAN |
| No Progress | 2/5/2025 | SEAN WIRCH |
| CofO in Progress | 2/5/2025 | SEAN WIRCH |
| Permit Finaled | 2/10/2025 | JOHN JANSON |
| Permit Finaled | 2/10/2025 | JOHN JANSON |
| CofO Issued | 2/10/2025 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 10/19/2023 | STEVEN WECHSLER |
| Address approval | Cleared | 10/20/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 11/6/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 2/8/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/8/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 2/26/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/28/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kaballo,, Amir; Lic. No.: C90707 | 152 S SWALL DR BEVERLY HILLS, CA 90211 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/13/2024 | Corrections Issued | HENRY KIM |
| Sewer | 3/13/2024 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 3/18/2024 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 3/26/2024 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 3/26/2024 | Partial Approval | HENRY KIM |
| Sewer | 3/26/2024 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 4/2/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 4/30/2024 | Not Ready for Inspection | JEFFREY BULL |
| Interior/Exterior Lathing | 7/22/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 7/22/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 8/28/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 8/28/2024 | Approved | JEFFREY BULL |
| Insulation | 9/10/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/10/2024 | Approved | JEFFREY BULL |
| Shower Pan | 9/10/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 9/13/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | ARUTYUN MADATYAN |
| Final | 11/20/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 11/20/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 11/20/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 11/20/2024 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 11/20/2024 | Approved | ARUTYUN MADATYAN |
| Final | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 1/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/27/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 1/29/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/31/2025 | Approved | ARUTYUN MADATYAN |
| Final | 1/31/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 1/31/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/31/2025 | Approved | ARUTYUN MADATYAN |