8515 W APPIAN WAY 90046
Certificate Information: 8515 W APPIAN WAY 90046
- Application / Permit
- 23016-10000-35748
- Plan Check / Job No.
- B23LA19237
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: (N) Detached 1-story ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part 2 of LAMC 12.22 A.33(c)-(d), (g)
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2023 | DAVID CASTILLO |
| Corrections Issued | 10/17/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/2/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/1/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/15/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/19/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 8/23/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 9/13/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 11/15/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 12/18/2024 | ALFREDO JARA |
| Plan Check Approved | 4/23/2025 | DAVID CASTILLO |
| Issued | 4/24/2025 | APPLICANT |
| CofO in Progress | 1/26/2026 | SCOTT FINNILA |
| Permit Finaled | 1/27/2026 | DEROLD HAUFF |
| CofO Issued | 1/27/2026 | DEROLD HAUFF |
| Permit Finaled | 1/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2023 | JEANIE LAM |
| Miscellaneous | Cleared | 10/8/2024 | ALBERT TAM |
| Roof/Waste drainage to street | Cleared | 11/5/2024 | JEANIE LAM |
| Sewer availability | Cleared | 11/7/2024 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 12/20/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Allcon Construction Inc; Lic. No.: 1036060-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2025 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 5/20/2025 | Partial Approval | ROY SPAULDING |
| Pre-Inspection | 6/24/2025 | Partial Inspection | BRENDAN MORELLI |
| Wood Frame | 6/24/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 7/23/2025 | Approved | ROY SPAULDING |
| HVAC-Rough | 7/23/2025 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 7/23/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 7/28/2025 | Approved | ROY SPAULDING |
| Green Building Rough | 7/28/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 7/28/2025 | Approved | ROY SPAULDING |
| Underground Mechanical | 7/28/2025 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 7/28/2025 | Approved | ROY SPAULDING |
| Wood Frame | 7/28/2025 | Approved | ROY SPAULDING |
| Insulation | 8/8/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 8/8/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 8/13/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 8/29/2025 | Approved | ROY SPAULDING |
| Final | 10/29/2025 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 10/29/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Not Ready | ROY SPAULDING |
| Service/Power Release | 10/29/2025 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 10/29/2025 | Approved | ROY SPAULDING |
| Final | 1/21/2026 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 1/21/2026 | Not Ready for Inspection | ROY SPAULDING |
| Final | 1/23/2026 | OK to Issue CofO | SCOTT FINNILA |
| Service/Power Release | 1/23/2026 | Approved | SCOTT FINNILA |