1500 N EL CENTRO AVE L6 90028
Certificate Information: 1500 N EL CENTRO AVE L6 90028
- Application / Permit
- 23016-10000-35704
- Plan Check / Job No.
- B23LA19187
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- FULL FLOOR (6th floor), NON-STRUCTURAL TENANT IMPROVEMENT FOR COMMERCIAL OFFICE. WORK INCLUDES MINOR INTERIOR DEMOLITION, INTERIOR PARTITIONS, SUSPEND CEILINGS, AND MILLWORK.
- Permit Issued
- Issued on 12/13/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/3/2024
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/22/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 10/23/2023 | APPLICANT |
| Applicant returned to address corrections | 11/28/2023 | LUKE GONZALES |
| Plan Check Approved | 12/12/2023 | AUNG SOE |
| Issued | 12/13/2023 | APPLICANT |
| Permit Finaled | 5/3/2024 | DAVID BURKHEAD |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 11/7/2023 | RAFAEL FONTES |
| Historic Resource Verification | Cleared | 11/7/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 12/7/2023 | DAVID URITA |
| Fire Marshal Fire Life Safety | Cleared | 12/11/2023 | FIRE DEPARTMENT |
Contact Information
| Architect | Kirk, Jeffrey Stewart; Lic. No.: C33107 | 830 PALLADIUM BLVD PALM SPRINGS, CA 92262 |
| Contractor | Bcci Construction Llc; Lic. No.: 492944-B | 1160 BATTERY STREET 250 SAN FRANCISCO, CA 94111 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 1/22/2024 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 1/26/2024 | Approved | RAFAEL CORTES |
| T-Bar Ceiling | 2/22/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| T-Bar Ceiling | 2/27/2024 | Partial Approval | JACOB MYERS |
| T-Bar Ceiling | 3/18/2024 | No Access for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 3/19/2024 | Approved | EDWIN GREGORYONA |
| Final | 4/9/2024 | Partial Inspection | DAVID BURKHEAD |
| Green Building Final | 4/9/2024 | Not Ready for Inspection | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV No Gas | DAVID BURKHEAD |
| Smoke Detectors | 4/9/2024 | Approved | DAVID BURKHEAD |
| Final | 5/3/2024 | Permit Finaled | DAVID BURKHEAD |
| Green Building Final | 5/3/2024 | Approved | DAVID BURKHEAD |