1133-1135 W 186TH ST 90248

Certificate Information: 1133-1135 W 186TH ST 90248

Application / Permit
23016-10000-35588
Plan Check / Job No.
B23LA19103
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 6582.2(E)(1)(A)
Permit Issued
Issued on 3/14/2024
Issuing Office
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2023 APPLICANT
Assigned to Plan Check Engineer 10/17/2023 LUISANGEL VALENZUELA
Corrections Issued 10/17/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/7/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 2/29/2024 ALEC MOUSAKHANIAN
Plan Check Approved 3/13/2024 ALEC MOUSAKHANIAN
Issued 3/14/2024 APPLICANT
CofO in Progress 2/26/2025 BEN MOLSTAD
CofO in Progress 3/7/2025 BEN MOLSTAD
CofO in Progress 4/1/2025 BEN MOLSTAD
Permit Finaled 4/1/2025 ANSON MAGLASANG
CofO Issued 4/1/2025 ANSON MAGLASANG
Permit Finaled 4/1/2025 ANSON MAGLASANG

Permit Application Clearance Information

Construction near power lines Cleared 12/14/2023 WALTER RAMIREZ
Address approval Cleared 12/20/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 12/21/2023 KHAING AYE
Sewer availability Cleared 1/9/2024 KHAING AYE

Contact Information

Contractor Owner-Builder       ,
Engineer Grandhi,, Venkata Rohit; Lic. No.: C88709 7823 BOXWOOD CT      HIGHLAND, CA 92346

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/12/2024 Corrections Issued BEN MOLSTAD
HVAC-Rough 12/12/2024 Not Ready for Inspection BEN MOLSTAD
MERV13>=Rough 12/12/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 12/18/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 12/18/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 12/18/2024 Approved BEN MOLSTAD
Pre-Inspection 1/6/2025 Approved BEN MOLSTAD
Wood Frame 1/6/2025 Not Ready for Inspection BEN MOLSTAD
Insulation 1/9/2025 Approved BEN MOLSTAD
Drywall Nailing 1/14/2025 Corrections Issued BEN MOLSTAD
Drywall Nailing 1/24/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 2/19/2025 Approved BEN MOLSTAD
Final 2/19/2025 Corrections Issued BEN MOLSTAD
MERV13>=Final 2/19/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Approved BEN MOLSTAD
Smoke Detectors 2/19/2025 Approved BEN MOLSTAD
Final 2/24/2025 Corrections Issued BEN MOLSTAD
Pre-Inspection 2/24/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 2/25/2025 Approved BEN MOLSTAD
Final 2/25/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 2/25/2025 Approved BEN MOLSTAD
PLUMBING-Final 2/25/2025 Approved BEN MOLSTAD
Final 3/7/2025 Corrections Issued BEN MOLSTAD
Final 3/28/2025 OK to Issue CofO BEN MOLSTAD