802 E 104TH ST 90002
Certificate Information: 802 E 104TH ST 90002
- Application / Permit
- 23016-10000-35504
- Plan Check / Job No.
- B23LA19049
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Exterior and interior remodel of existing 1-story single family dwelling. All work per WFPP. NFPA13D-Fire sprinkler system throughout. Existing SFD address to be RE-ASSIGNED to the following address: 802 E 104th St
- Permit Issued
- Issued on 2/8/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/15/2024
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2023 | VICTOR CHEN |
| Corrections Issued | 10/11/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 1/22/2024 | MINA HABILI |
| Applicant returned to address corrections | 2/6/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/8/2024 | AUNG SOE |
| Issued | 2/8/2024 | APPLICANT |
| Permit Finaled | 9/13/2024 | BARRY HACHE |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/22/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 2/14/2024 | Corrections Issued | JAMES CHAVEZ |
| Special/Order Compliance | 2/14/2024 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 2/16/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 3/14/2024 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/20/2024 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/27/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 3/27/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 4/2/2024 | Partial Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/2/2024 | Conditional Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/15/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 4/15/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 4/15/2024 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/15/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 4/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Shower Pan | 4/15/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/2/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/2/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 5/2/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/6/2024 | Approved | BEN MOLSTAD |
| Insulation | 5/8/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 5/14/2024 | Approved | BEN MOLSTAD |
| Final | 8/26/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 8/26/2024 | Approved | BARRY HACHE |
| Special/Order Compliance | 8/26/2024 | Partial Approval | BEN MOLSTAD |
| Final | 9/3/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Approved | BARRY HACHE |
| Final | 9/9/2024 | Corrections Issued | BARRY HACHE |
| Final | 9/13/2024 | Permit Finaled | BARRY HACHE |