8842-8844 S KITTYHAWK AVE 90045

Certificate Information: 8842-8844 S KITTYHAWK AVE 90045

Application / Permit
23016-10000-35426
Plan Check / Job No.
B23LA19014
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan CONVERT EXISTING ATTACHED GARAGEOF (E) SFD INTO ATTACHED JADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/20/2024
Issuing Office
Current Status
CofO Issued on 11/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 JASON JANGADA
Corrections Issued 10/13/2023 JASON JANGADA
Applicant returned to address corrections 11/30/2023 CAROLEAN BASMA
Plan Check Approved 12/5/2023 JASON JANGADA
Issued 2/20/2024 APPLICANT
CofO in Progress 11/4/2024 BOBBY KEY
Permit Finaled 11/5/2024 RICHARD STEINBACH
Permit Finaled 11/5/2024 RICHARD STEINBACH
CofO Issued 11/5/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/17/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 10/17/2023 DARIN LAM
Sewer availability Cleared 10/17/2023 DARIN LAM
Specific Plan Cleared 10/23/2023 ALESSANDRO MERCURI

Contact Information

Contractor Build Tuff Construction; Lic. No.: 1076283-B       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/7/2024 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 3/11/2024 Approved BOBBY KEY
PLUMBING-Rough 3/19/2024 Partial Approval BOBBY KEY
Underground Mechanical 3/19/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 4/16/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 4/16/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 4/17/2024 No Access for Inspection TEMISTOCLES CAAL
HVAC-Rough 4/17/2024 No Access for Inspection TEMISTOCLES CAAL
Insulation 4/22/2024 Partial Approval BOBBY KEY
Insulation 4/24/2024 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 4/24/2024 Approved JESUS RODRIGUEZ
Shower Pan 4/24/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Corrections Issued BOBBY KEY
HVAC-Rough 4/30/2024 Approved BOBBY KEY
Insulation 4/30/2024 Approved BOBBY KEY
Smoke Detectors 4/30/2024 Corrections Issued BOBBY KEY
Special/Order Compliance 4/30/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 5/17/2024 Partial Approval BOBBY KEY
Interior/Exterior Lathing 5/17/2024 Approved BOBBY KEY
Deputy Wood Construction 5/24/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 5/28/2024 Approved BOBBY KEY
Drywall Nailing 5/31/2024 Approved BOBBY KEY
ELECTRICAL-Final 10/7/2024 Approved BOBBY KEY
Final 10/7/2024 Corrections Issued BOBBY KEY
HVAC-Final 10/7/2024 Approved BOBBY KEY
PLUMBING-Final 10/7/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 10/7/2024 Approved BOBBY KEY
PLUMBING-Final 10/8/2024 Approved TEMISTOCLES CAAL
Final 11/4/2024 OK to Issue CofO BOBBY KEY