11608 W MORAGA LANE 90049

Certificate Information: 11608 W MORAGA LANE 90049

Application / Permit
23016-10000-35425
Plan Check / Job No.
B23LA19011
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Install (N) Residential elevator shaft for a hydraulic elevator in (E) 2-Story SFD w/Attached Garage. Elevator Approximate 48 S.F.
Permit Issued
Issued on 11/15/2023
Issuing Office
Current Status
Permit Finaled on 8/22/2024

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 ALFREDO JARA
Corrections Issued 10/14/2023 ALFREDO JARA
Plan Check Approved 11/12/2023 DAVID CASTILLO
Issued 11/15/2023 APPLICANT
Permit Finaled 8/21/2024 CARLOS MATAMOROS

Permit Application Clearance Information

ZI Cleared 10/17/2023 DANIEL CORONADO
Grading Pre-Inspection Cleared 11/12/2023 ALFREDO JARA

Contact Information

Contractor Mat West Company The; Lic. No.: 512829-B PO BOX 7220      VAN NUYS, CA 91409
Engineer Chiu,, Frankie Wai-King; Lic. No.: C43852 2106 TONDOLEA LN      LA CANADA, CA 91011

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/21/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 11/21/2023 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 11/27/2023 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 12/4/2023 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 12/4/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 12/29/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 12/29/2023 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/4/2024 Approved CARLOS MATAMOROS
Deputy Steel/Welding 1/4/2024 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/4/2024 Approved CARLOS MATAMOROS
Insulation 1/8/2024 Approved CARLOS MATAMOROS
Drywall Nailing 2/6/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Final 7/11/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/20/2024 SGSOV Approved CARLOS MATAMOROS
Final 8/21/2024 Permit Finaled CARLOS MATAMOROS
Smoke Detectors 8/21/2024 Approved CARLOS MATAMOROS