5110 E IRVINGTON PL 90042
Certificate Information: 5110 E IRVINGTON PL 90042
- Application / Permit
- 23016-10000-34577
- Plan Check / Job No.
- B23LA18736
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMODEL OF (E) DUPLEX WITH BREEZEWAY TO ADD A NEW BEDROOM AND BATHROOM ON BOTH FLOORS, RELOCATE KITCHEN, AND REPAIR WALLS FROM WATER DAMAGE.. REPAIR (E) BREEZEWAY BETWEEN UNITS. WORK TO BE DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/28/2024
- Issuing Office
- Current Status
- Permit Finaled on 7/19/2024
Permit Application Status History
| Submitted | 10/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/7/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/28/2023 | MADISON ODELL |
| Applicant returned to address corrections | 11/1/2023 | MADISON ODELL |
| Applicant returned to address corrections | 1/5/2024 | MADISON ODELL |
| Plan Check Approved | 2/6/2024 | MADISON O'DELL |
| Issued | 3/28/2024 | APPLICANT |
| Permit Finaled | 7/18/2024 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | CELINA MORENO |
| Sewer availability | Cleared | 10/24/2023 | CELINA MORENO |
Contact Information
| Contractor | Fast Track Builders; Lic. No.: 1075351-B | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/5/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/5/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/5/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/5/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 4/8/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/9/2024 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/9/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 4/9/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 4/16/2024 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 4/16/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/18/2024 | Approved | BRIAN SULLIVAN |
| Insulation | 4/18/2024 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/18/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 4/18/2024 | Partial Approval | BRIAN SULLIVAN |
| Drywall Nailing | 4/26/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/26/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/26/2024 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 7/3/2024 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Final | 7/3/2024 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| HVAC-Final | 7/3/2024 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| PLUMBING-Final | 7/3/2024 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | CHARLES BOGHOSKHAN |
| Smoke Detectors | 7/3/2024 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Rough | 7/15/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 7/15/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Special/Order Compliance | 7/15/2024 | Partial Inspection | SCOTT FINNILA |
| Final | 7/18/2024 | Permit Finaled | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | CRAIG VAUGHAN |