10717 W ADDISON ST 1-3 91601

Certificate Information: 10717 W ADDISON ST 1-3 91601

Application / Permit
23016-10000-34213
Plan Check / Job No.
B23LA18571
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert part of (E) Garage on the 1st Floor of (E) 3-Story Duplex to ADU Per CA Govt. Code 65852.2(e)(1)(C) -ADU sprinklered thru-out
Permit Issued
Issued on 1/13/2025
Issuing Office
Metro
Current Status
CofO Issued on 3/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 MAHNAZ NOURHASHEMI
Corrections Issued 10/19/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 10/20/2023 KEN GILL
Building Plans Picked Up 10/26/2023 APPLICANT
Plan Check Approved 8/22/2024 MAHNAZ NOURHASHEMI
Issued 1/13/2025 APPLICANT
CofO in Progress 12/1/2025 ROBERTO PALACIOS-LOPEZ
CofO in Progress 1/13/2026 RAUL OLAGI
CofO in Progress 3/4/2026 RAUL OLAGI
Permit Finaled 3/5/2026 RUBEN SALAS
CofO Issued 3/5/2026 RUBEN SALAS
Permit Finaled 3/5/2026 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 8/8/2024 EDGAR ALCARAZ
Address approval Cleared 8/15/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/13/2025 BIJAN ZADEH

Contact Information

Contractor Entourage Home Remodeling; Lic. No.: 1075374-B 1450 N TUSTIN AVE #115      SANTA ANA, CA 92705
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Pre-Inspection 1/17/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/3/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/11/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/11/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 4/4/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/5/2025 Approved RAUL OLAGI
HVAC-Rough 6/5/2025 Approved RAUL OLAGI
Wood Frame 6/5/2025 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 6/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/9/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/9/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/26/2025 Approved RAUL OLAGI
Sewer 6/26/2025 Approved RAUL OLAGI
Interior/Exterior Lathing 7/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 7/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 10/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 10/9/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 11/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 11/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 11/21/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 1/13/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/4/2026 OK to Issue CofO RAUL OLAGI