4508-4508 1/2 E BEND DR 90065

Certificate Information: 4508-4508 1/2 E BEND DR 90065

Application / Permit
23016-10000-33825
Plan Check / Job No.
B23LA18376
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN CONVERT EXISTING STORAGE WITHIN (E) SFD TO NEW 340 SF ADU PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER ENG.
Permit Issued
Issued on 11/8/2023
Issuing Office
Current Status
CofO Issued on 11/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2023 APPLICANT
Assigned to Plan Check Engineer 10/4/2023 NEHEMIAS RAMOS
Corrections Issued 10/5/2023 NEHEMIAS RAMOS
Applicant returned to address corrections 10/12/2023 LUISANGEL VALENZUELA
Plan Check Approved 11/7/2023 LUISANGEL VALENZUELA
Issued 11/8/2023 APPLICANT
CofO in Progress 11/21/2025 NICHOLAS LOPEZ
Permit Finaled 11/23/2025 DEROLD HAUFF
CofO Issued 11/23/2025 DEROLD HAUFF
Permit Finaled 11/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/14/2023 CELINA MORENO
Sewer availability Cleared 10/14/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/17/2023 CELINA MORENO
Miscellaneous Cleared 11/1/2023 ALBERT TAM
Miscellaneous Cleared 11/2/2023 PABLO ESTRADA
Miscellaneous Cleared 11/2/2023 PABLO ESTRADA
Miscellaneous Cleared 11/2/2023 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/26/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 2/26/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/26/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 12/18/2024 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 12/18/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 2/26/2025 Approved NICHOLAS LOPEZ
Green Building Rough 2/26/2025 Approved NICHOLAS LOPEZ
Insulation 2/26/2025 Approved NICHOLAS LOPEZ
Insulation 3/10/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 3/20/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 11/14/2025 Corrections Issued NICHOLAS LOPEZ
Final 11/14/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 11/14/2025 Approved NICHOLAS LOPEZ
HVAC-Final 11/14/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 11/14/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 11/14/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 11/21/2025 Approved NICHOLAS LOPEZ
Final 11/21/2025 OK to Issue CofO NICHOLAS LOPEZ