3912 S VIRGINIA ROAD 90008

Certificate Information: 3912 S VIRGINIA ROAD 90008

Application / Permit
23016-10000-33772
Plan Check / Job No.
B23LA18359
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. Conversion of Detached Garage and portion of Storage Room to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work per Wood Frame Prescriptive Provisions
Permit Issued
Issued on 3/1/2024
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/6/2023 EDWIN ESPIN
Corrections Issued 10/10/2023 EDWIN ESPIN
Applicant returned to address corrections 10/19/2023 CARLOS MONTES
Plan Check Approved 2/6/2024 KEVIN MORALES
Issued 3/1/2024 APPLICANT
CofO in Progress 6/24/2025 LUIS CASTRO
Permit Finaled 6/26/2025 DEROLD HAUFF
CofO Issued 6/26/2025 DEROLD HAUFF
Permit Finaled 6/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/16/2023 JUSTIN BICOL
Sewer availability Cleared 10/16/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 10/17/2023 JUSTIN BICOL
Construction near power lines Cleared 1/24/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/23/2024 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 12/23/2024 Partial Approval LUIS CASTRO
PLUMBING-Rough 12/23/2024 Partial Approval LUIS CASTRO
Underground Mechanical 12/23/2024 Approved LUIS CASTRO
Reinforced Concrete Frame 1/23/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 2/19/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 2/19/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 2/21/2025 Approved LUIS CASTRO
HVAC-Rough 2/21/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 2/25/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved LUIS CASTRO
Green Building Rough 2/25/2025 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 2/27/2025 Partial Approval LUIS CASTRO
Green Building Rough 2/27/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 2/27/2025 Approved LUIS CASTRO
Pre-Inspection 2/27/2025 Partial Inspection RAUL BARAJAS
Special/Order Compliance 2/27/2025 Partial Inspection RAUL BARAJAS
Insulation 3/17/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 3/17/2025 Partial Approval LUIS CASTRO
Drywall Nailing 3/28/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/28/2025 Approved ARTHUR NEGRETE
Service/Power Release 5/1/2025 Corrections Issued LUIS CASTRO
Underground Mechanical 5/1/2025 Approved LUIS CASTRO
ELECTRICAL-Final 6/3/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 6/5/2025 Corrections Issued LUIS CASTRO
Final 6/5/2025 Corrections Issued LUIS CASTRO
HVAC-Final 6/5/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 6/5/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 6/18/2025 Approved LUIS CASTRO
ELECTRICAL-Final 6/18/2025 Approved LUIS CASTRO
Final 6/18/2025 OK to Issue CofO LUIS CASTRO
Green Building Final 6/18/2025 Approved LUIS CASTRO
Green Building Rough 6/18/2025 Approved LUIS CASTRO
HVAC-Final 6/18/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 6/18/2025 Approved LUIS CASTRO