1429 1/2 E 54TH ST 90011
Certificate Information: 1429 1/2 E 54TH ST 90011
- Application / Permit
- 23016-10000-33238
- Plan Check / Job No.
- B23LA18049
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR/EXTERIOR ALTERATION TO EXISTING SFD FOR FIRE DAMAGE REPAIR. SCOPE TO INCLUDE COMPLETELY (N) ROOF, (N) INTERIOR CONTINUOUS FOOTINGS, (N) WINDOWS, REPLACE FIRE DAMAGEED WALLS PER PLANS, (N) STUCCO FINISH THROUGHOUT, AND FLOORING.
- Permit Issued
- Issued on 11/14/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/27/2025
Permit Application Status History
| Submitted | 9/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | SAMUEL GONZALEZ |
| Corrections Issued | 10/1/2023 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 10/6/2023 | APPLICANT |
| Applicant returned to address corrections | 10/31/2023 | MINA HABILI |
| Plan Check Approved | 11/7/2023 | LUKE GONZALES |
| Issued | 11/14/2023 | APPLICANT |
| Permit Finaled | 10/27/2025 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/6/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2023 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 2/10/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/3/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 3/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/12/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 7/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 7/10/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 7/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 7/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/14/2025 | Approved | STUART CHAPMAN |
| Final | 10/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/27/2025 | Permit Finaled | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/27/2025 | Approved | ALEJANDRO DE ARTOLA |