450 E SOUTH VENICE BLVD 90291
Certificate Information: 450 E SOUTH VENICE BLVD 90291
- Application / Permit
- 23016-10000-33054
- Plan Check / Job No.
- B23LA17949
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (N) SCCS
- Permit Issued
- Issued on 11/19/2025
- Issuing Office
- Current Status
- CofC Issued on 4/28/2026
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | JESSE VIDUYA |
| Corrections Issued | 10/10/2023 | JESSE VIDUYA |
| Quality Review Completed | 10/17/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/19/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 9/3/2025 | JESSE VIDUYA |
| Plan Check Approved | 10/17/2025 | VARAND SARKISIAN |
| Issued | 11/19/2025 | APPLICANT |
| OK for CofC | 4/27/2026 | FARHAD DADBIN |
| CofC Issued | 4/28/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 11/4/2025 | RAFAEL FONTES |
| Historic monument | Cleared | 11/4/2025 | RAFAEL FONTES |
| Tenant Habitability Plan | Cleared | 11/17/2025 | KORNEL LELEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Watson,, Darren; Lic. No.: NA87717 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/3/2025 | Approved | RICARDO ROBLES |
| Deputy Steel/Welding | 1/30/2026 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 2/10/2026 | Corrections Issued | FARHAD DADBIN |
| Deputy Steel/Welding | 2/11/2026 | Approved | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 2/17/2026 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/18/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Structural Steel Frame | 2/18/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/27/2026 | Approved | FARHAD DADBIN |
| Structural Steel Frame | 2/27/2026 | Approved | FARHAD DADBIN |
| Deputy Reinf. Concrete | 3/2/2026 | Conditional Approval | FARHAD DADBIN |
| Structural Steel Frame | 3/4/2026 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 3/23/2026 | Approved | DANIEL VARNUM |
| Final | 4/27/2026 | OK for CofC | FARHAD DADBIN |
| METHANE-Final | 4/27/2026 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 4/27/2026 | Approved | FARHAD DADBIN |