2002 S COTNER AVE 90025
Certificate Information: 2002 S COTNER AVE 90025
- Application / Permit
- 23016-10000-32644
- Plan Check / Job No.
- B23LA17820
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Day Care Facility, dogs and cats
- Work Description
- CHANGE OF USE FROM EXISTING WAREHOUSE AND OFFICE TO DOG TRAINING AND DAY CARE FACILITY. NO OVERNIGHT BOARDING.
- Permit Issued
- Issued on 10/23/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | SAMUEL GONZALEZ |
| Corrections Issued | 9/30/2023 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 10/4/2023 | APPLICANT |
| Plan Check Approved | 10/20/2023 | CRISTINA SALAZAR |
| Issued | 10/23/2023 | APPLICANT |
| Permit Finaled | 9/26/2024 | DAVID TSAU |
| CofO Issued | 9/26/2024 | DAVID TSAU |
| Permit Finaled | 9/26/2024 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/13/2023 | DARIN LAM |
| ZA Case | Cleared | 10/13/2023 | MATHEW QUAN |
Contact Information
| Architect | Alomar,, Rania; Lic. No.: C29809 | 7523 NORTON AVENUE WEST HOLLYWOOD, CA 90046 |
| Contractor | Yourico Construction Inc; Lic. No.: 594159-B | 1241 N THOMPSON AVENUE GLENDALE, CA 91201 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 1/8/2024 | Corrections Issued | MICHAEL PETRUSKO |
| Wood Frame | 1/11/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Wood Frame | 2/21/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 3/1/2024 | Partial Approval | RICARDO ROBLES |
| Wood Frame | 3/28/2024 | Partial Approval | RICARDO ROBLES |
| Wood Frame | 4/12/2024 | Approved | RICARDO ROBLES |
| Drywall Nailing | 4/23/2024 | Approved | RICARDO ROBLES |
| T-Bar Ceiling | 6/17/2024 | Approved | MICHAEL PETRUSKO |
| Final | 7/29/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 7/29/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 8/2/2024 | Corrections Issued | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 8/2/2024 | Approved | GRANT WOODS |
| Special/Order Compliance | 8/2/2024 | Not Ready for Inspection | GRANT WOODS |
| Final | 8/21/2024 | Conditional Approval | MICHAEL PETRUSKO |