2002 S COTNER AVE 90025

Certificate Information: 2002 S COTNER AVE 90025

Application / Permit
23016-10000-32644
Plan Check / Job No.
B23LA17820
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Day Care Facility, dogs and cats
Work Description
CHANGE OF USE FROM EXISTING WAREHOUSE AND OFFICE TO DOG TRAINING AND DAY CARE FACILITY. NO OVERNIGHT BOARDING.
Permit Issued
Issued on 10/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 SAMUEL GONZALEZ
Corrections Issued 9/30/2023 SAMUEL GONZALEZ
Building Plans Picked Up 10/4/2023 APPLICANT
Plan Check Approved 10/20/2023 CRISTINA SALAZAR
Issued 10/23/2023 APPLICANT
Permit Finaled 9/26/2024 DAVID TSAU
CofO Issued 9/26/2024 DAVID TSAU
Permit Finaled 9/26/2024 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/13/2023 DARIN LAM
Sewer availability Cleared 10/13/2023 DARIN LAM
ZA Case Cleared 10/13/2023 MATHEW QUAN

Contact Information

Architect Alomar,, Rania; Lic. No.: C29809 7523 NORTON AVENUE      WEST HOLLYWOOD, CA 90046
Contractor Yourico Construction Inc; Lic. No.: 594159-B 1241 N THOMPSON AVENUE      GLENDALE, CA 91201

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 1/8/2024 Corrections Issued MICHAEL PETRUSKO
Wood Frame 1/11/2024 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 2/21/2024 Not Ready for Inspection FARHAD DADBIN
Footing/Foundation/Slab 3/1/2024 Partial Approval RICARDO ROBLES
Wood Frame 3/28/2024 Partial Approval RICARDO ROBLES
Wood Frame 4/12/2024 Approved RICARDO ROBLES
Drywall Nailing 4/23/2024 Approved RICARDO ROBLES
T-Bar Ceiling 6/17/2024 Approved MICHAEL PETRUSKO
Final 7/29/2024 Not Ready for Inspection MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Not Ready MICHAEL PETRUSKO
Smoke Detectors 7/29/2024 Not Ready for Inspection MICHAEL PETRUSKO
Final 8/2/2024 Corrections Issued GRANT WOODS
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved GRANT WOODS
Smoke Detectors 8/2/2024 Approved GRANT WOODS
Special/Order Compliance 8/2/2024 Not Ready for Inspection GRANT WOODS
Final 8/21/2024 Conditional Approval MICHAEL PETRUSKO