3353 1/4 E HOLYOKE DR 90065
Certificate Information: 3353 1/4 E HOLYOKE DR 90065
- Application / Permit
- 23016-10000-32350
- Plan Check / Job No.
- B23LA17684
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) 440 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
- Permit Issued
- Issued on 3/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/3/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/11/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/17/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 1/23/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 1/30/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 2/12/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/29/2024 | LUISANGEL VALENZUELA |
| Issued | 3/3/2024 | APPLICANT |
| CofO in Progress | 5/5/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/12/2023 | DAVID LOPEZ |
| Miscellaneous | Cleared | 12/8/2023 | PABLO ESTRADA |
| Specific Plan | Cleared | 12/8/2023 | PABLO ESTRADA |
| ZI | Cleared | 12/8/2023 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2023 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 1/30/2024 | KAMYAR EMAMI |
| Address approval | Cleared | 2/9/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/7/2024 | Conditional Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 6/7/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 6/10/2024 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/27/2024 | No Access for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/1/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 7/29/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/5/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 8/5/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/5/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/7/2024 | No Access for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/9/2024 | No Access for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/13/2024 | Partial Approval | THOMAS LOGRASSO |
| Wood Frame | 8/13/2024 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/15/2024 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 8/15/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 8/15/2024 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 8/15/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 9/6/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 1/24/2025 | Partial Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 2/3/2025 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 3/4/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 3/4/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/4/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 3/4/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/4/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 3/4/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/12/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 3/12/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/12/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 3/12/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/17/2025 | Approved | NICHOLAS LOPEZ |
| Final | 3/17/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Final | 3/17/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/17/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Final | 3/27/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 5/5/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 5/5/2025 | Approved | NICHOLAS LOPEZ |