1724 W 51ST ST 90062
Certificate Information: 1724 W 51ST ST 90062
- Application / Permit
- 23016-10000-31888
- Plan Check / Job No.
- B23LA17441
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing detached garage and hobby room to ADU per CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/16/2024
- Issuing Office
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2023 | DANIEL SMILEY |
| Corrections Issued | 9/25/2023 | DANIEL SMILEY |
| Plan Check Approved | 9/18/2024 | DANIEL SMILEY |
| Issued | 11/16/2024 | APPLICANT |
| CofO in Progress | 9/11/2025 | SABAS ALONSO |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/2/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2023 | JUSTIN BICOL |
| Address approval | Cleared | 10/27/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 12/26/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/26/2023 | RIDWAN HARDY |
| Miscellaneous | Cleared | 8/26/2024 | ALBERT TAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/25/2025 | Conditional Approval | ALEX COLIN |
| Footing/Foundation/Slab | 4/9/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/5/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/5/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/5/2025 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 5/15/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 5/15/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 5/16/2025 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 5/16/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 5/16/2025 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/29/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 5/29/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 5/29/2025 | Approved | WAYNE REGESTER |
| Insulation | 6/2/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 6/10/2025 | Approved | ALEX COLIN |
| Gas Test | 7/11/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 7/11/2025 | Approved | ANTHONY RAMOS |
| Sewer | 7/11/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 7/11/2025 | Approved | ANTHONY RAMOS |
| Final | 8/7/2025 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/7/2025 | Approved | SABAS ALONSO |
| Final | 9/8/2025 | OK to Issue CofO | SABAS ALONSO |