1724 W 51ST ST 90062

Certificate Information: 1724 W 51ST ST 90062

Application / Permit
23016-10000-31888
Plan Check / Job No.
B23LA17441
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert existing detached garage and hobby room to ADU per CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 11/16/2024
Issuing Office
Current Status
CofO Issued on 9/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 DANIEL SMILEY
Corrections Issued 9/25/2023 DANIEL SMILEY
Plan Check Approved 9/18/2024 DANIEL SMILEY
Issued 11/16/2024 APPLICANT
CofO in Progress 9/11/2025 SABAS ALONSO
Permit Finaled 9/13/2025 DEROLD HAUFF
CofO Issued 9/13/2025 DEROLD HAUFF
Permit Finaled 9/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 10/2/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/11/2023 JUSTIN BICOL
Address approval Cleared 10/27/2023 JEANIE LAM
Construction near power lines Cleared 12/26/2023 RIDWAN HARDY
Construction within easement Cleared 12/26/2023 RIDWAN HARDY
Miscellaneous Cleared 8/26/2024 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/25/2025 Conditional Approval ALEX COLIN
Footing/Foundation/Slab 4/9/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 5/5/2025 Approved SABAS ALONSO
HVAC-Rough 5/5/2025 Approved SABAS ALONSO
Underground Mechanical 5/5/2025 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 5/15/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 5/15/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 5/16/2025 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 5/16/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 5/16/2025 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 5/29/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 5/29/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 5/29/2025 Approved WAYNE REGESTER
PLUMBING-Rough 5/29/2025 Approved WAYNE REGESTER
Insulation 6/2/2025 Approved ANTHONY RAMOS
Drywall Nailing 6/10/2025 Approved ALEX COLIN
Gas Test 7/11/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 7/11/2025 Approved ANTHONY RAMOS
Sewer 7/11/2025 Approved ANTHONY RAMOS
Underground Mechanical 7/11/2025 Approved ANTHONY RAMOS
Final 8/7/2025 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 8/7/2025 Approved SABAS ALONSO
Final 9/8/2025 OK to Issue CofO SABAS ALONSO